A takes 6 days less than B to do a work. If both A and B working together can do it in 4 days, how many days will B take to finish it?
The correct Answer is:B can finish work in 12 days. A can finish work in 6 days.
Topper's Solved these Questions
- BOOK - OSWAL PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - Evaluation and Analysis Based Question10videos
QUADRATIC EQUATIONS
- BOOK - OSWAL PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - Assertion and Reasoning Based Question2videos
QUADRATIC EQUATIONS
- BOOK - OSWAL PUBLICATIONCHAPTER - QUADRATIC EQUATIONSEXERCISE - Short Answer Type Question27videos
QUADRATIC EQUATIONS
- BOOK - OSWAL PUBLICATIONCHAPTER - PROBABILITYEXERCISE - Self Assessment66videos
PROBABILITY
- BOOK - OSWAL PUBLICATIONCHAPTER - REAL NUMBERSEXERCISE - Self-Assessment11videos
REAL NUMBERS
Similar Questions
B takes 16 days less than A to do a certain piece of work. If both working together can complete the work in 15 days, in how many days will B alone complete the work ?
View SolutionA takes 9 days more than B to do a certain piece of work. Together they can do the work in 6 days. How many days will A alone take to do the work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?
A8 daysB12 daysC10 daysD16 days - Question 2 - Select One
X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?A30 daysB27 daysC20 daysD25 days
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View SolutionA takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
View SolutionAnand takes 9 days more than his father to do a certain piece of work. Together they can do the work in 6 days. How many days will Anand take to do that work alone?
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View SolutionA takes 10 days less than the time taken by B to finish a piece of work. If both A and 6 can do it in 12 days, then the time taken by B alone to finish the work is
View SolutionAcan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View Solution