Doubtnut Promotions Sticky

A takes 6 days less than B to do a work. If both A and B working together can do it in 4 days, how many days will B take to finish it?

Text Solution
Verified by Experts

The correct Answer is:B can finish work in 12 days. A can finish work in 6 days.

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 4 days. B and C together can do it in 3 days, while A and C together can do it in 2 days. How many days will B take to do the work alone?

    A8 days
    B12 days
    C10 days
    D16 days
  • Question 2 - Select One

    X takes 10 days less than the time taken by Y to finish a piece of work, if both X and Y together finish a work in 12 days. Find the time taken by Y to finish the work.
    X, किसी कार्य को पूरा करने में Y की तुलना में 10 दिन का कम समय लेता है | X और Y दोनों मिलकर कार्य को 12 दिन में पूरा कर सकते हैं | Y कितने दिनों में अकेले कार्य को पूरा करेगा?

    A30 days
    B27 days
    C20 days
    D25 days