Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48 days, respectively. Amar, Bhavan and Chetan started it. After 6 days, Amar left. The order tow continued to work. Bhavanleft 15 days the comletion work. Bhava left 15 days, before the completeion of the job. Chetan comlete the remaining work. Find the total time teaken to complet the job . ( in days)
21
24
27
30
The correct Answer is:B
Amar worked for 6 days.
Bhavan woked for (t-15) days
Chetan worked for t days,
Job=6(124)+(t−15)(136)+t(148)=1
14+t(136+148)−512=1
7t144=76
t=24
Topper's Solved these Questions
Similar Questions
A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View Solution
Knowledge Check
X,Y and Z can complete a job in 24 days, 32 days and 48 days respectively. They worked together and earned a total of ₹ x.Find the ratio of their shares.
A4:3:2B3:2:1C5:4:3D6:5:4A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
A10B20C15D25A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of these
A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is:
A, B और C अकेले-अकेले किसी कार्य को क्रमशः 24, 15 और 12 दिनों में पूरा कर सकते हैं |B और C ने कार्य करना शुरू किया तथा 3 दिनों तक कार्य करके छोड़ दिया| शेष कार्य अकेले पूरा करने में A को कितने दिन लगेंगे ?
View SolutionA, B and C can individually complete a piece of work in 24 days, 15 days and 12 days. respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is :
View SolutionM and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C start the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is:
A, B और C व्यक्तिगत रूप से किसी कार्य को क्रमशः 24, 16 और 32 दिनों में पूरा कर सकते हैं | यदि A और C ने कार्य शुरू किया तथा 6 दिनों तक कार्य करके छोड़ दिया, तो शेष कार्य पूरा करने में B को कितने दिन लगेंगे ?
View Solution