Doubtnut Promotions Sticky

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A

a)20

B

b)19

C

c)30

D

d)31

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, we need to determine how many days C worked when A, B, and C worked together on a piece of work, with A leaving after 9 days and B leaving 3 days before the work was completed.

1. Determine the Work Rates of A, B, and C:
- A can complete the work in 24 days, so A's work rate is 124 of the work per day.
- B can complete the work in 36 days, so B's work rate is 136 of the work per day.
- C can complete the work in 108 days, so C's work rate is 1108 of the work per day.

2. Calculate the Total Work:
- The least common multiple (LCM) of 24, 36, and 108 is 216. Therefore, the total work can be considered as 216 units.

3. Calculate the Individual Work Rates in Units:
- A's work rate: 21624=9 units per day.
- B's work rate: 21636=6 units per day.
- C's work rate: 216108=2 units per day.

4. Calculate Work Done in the First 9 Days:
- In the first 9 days, A, B, and C work together:
- Total work done in 9 days = (9+6+2)×9=17×9=153 units.

5. Determine Remaining Work:
- Remaining work after 9 days = Total work - Work done in 9 days
- Remaining work = 216153=63 units.

6. Calculate the Work Done by B and C:
- B leaves 3 days before the work is completed, meaning B works for T3 days, where T is the total time taken to complete the work.
- Let x be the number of days B worked after A left. Hence, C worked for x+3 days.

7. Work Done by B and C Together:
- Work done by B and C in the remaining days = (6+2)×x=8x.
- Since they need to complete the remaining 63 units, we have:
- 8x=63
- x=638=7.875 days.

8. Total Days Worked:
- Total days worked by C = Days worked together + Days worked after A left
- C worked for 9 days (with A and B) + 7.875 days (with B) = 9+7.875=16.875 days.

9. Final Calculation:
- Since B left 3 days before the work was completed, C worked for an additional 3 days alone to finish the work.
- Therefore, total days C worked = 16.875+3=19.875 days.

Conclusion:
C worked for approximately 20 days.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 2 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10