Doubtnut Promotions Sticky

Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

A

30 days

B

45 days

C

60 days

D

15 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day. by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

    A30 days
    B45 days
    C60 days
    D15 days
  • Question 1 - Select One

    If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?

    A30
    B25
    C48
    D35
  • Question 1 - Select One

    If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

    AA. 16
    BB. 15
    CC. 10
    DD. 12
  • Question 1 - Select One

    15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days

    A5 hours
    B10 hours
    C15 hours
    D18 hours
  • Question 1 - Select One

    If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?

    A10
    B20
    C30
    D40

Similar Questions