If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
10
20
30
40
The correct Answer is:C
Let the required number of men be x.
We have,
.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO, PROPORTION AND VARIATIONEXERCISE - Leval 220videos
RATIO, PROPORTION AND VARIATION
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - QUADRATIC EXPRESSIONS AND EQUATIONSEXERCISE - Level 323videos
QUADRATIC EXPRESSIONS AND EQUATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - SALES TAX AND COST OF LIVING INDEX EXERCISE - Level 314videos
SALES TAX AND COST OF LIVING INDEX
Similar Questions
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
If 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
A21B20C24D22 - Question 2 - Select One
If 15 men can do a work in 48 days, then how many men will be required to complete the work in 30 days ?
A,21B20C24D22 - Question 3 - Select One
7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
A28B21C14D7
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View SolutionTwelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?
View Solution