12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
The correct Answer is:270 men
To solve the problem, we will follow these steps:
Step 1: Calculate the total work done by 12 men in 30 days working 9 hours a day.
Total work (in man-hours) = Number of men × Number of days × Number of hours per day
Total work = 12 men × 30 days × 9 hours/day
Total work = 12 × 30 × 9 = 3240 man-hours
Step 2: Determine the total work required for 10 times this work.
Since we need to complete 10 times the original work:
Total work required = 10 × 3240 man-hours
Total work required = 32400 man-hours
Step 3: Calculate the total available work hours with the new conditions.
Now, we need to find out how many men are required to complete this work in 24 days working 5 hours a day.
Total available work hours = Number of men × Number of days × Number of hours per day
Let the number of men required be N.
Total available work hours = N men × 24 days × 5 hours/day
Total available work hours = N×24×5=120N man-hours
Step 4: Set up the equation.
We know that the total available work hours must equal the total work required:
120N = 32400
Step 5: Solve for N.
To find N, divide both sides of the equation by 120:
N = 32400 / 120
N = 270
Conclusion:
The number of men required to complete 10 times the work in 24 days by working 5 hours a day is 270 men.
---
Total work = 12 × 30 × 9 = 3240 man-hours
Total work required = 32400 man-hours
Let the number of men required be N.
Total available work hours = N×24×5=120N man-hours
N = 270
Topper's Solved these Questions
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (a)27videos
TIME AND WORK
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 20 (b)15videos
TIME AND WORK
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SURDS EXERCISE - UNIT TEST -115videos
SURDS
- BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLES EXERCISE - Self Assessment Sheet10videos
TRIANGLES
Similar Questions
Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
- Question 1 - Select One
If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?
A30B25C48D35 - Question 2 - Select One
If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
Aa) 15Bb) 12Cc) 10Dd) 16 - Question 3 - Select One
18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day
A32 daysB45 daysC36 daysD40 days
If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
View SolutionIf 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?
View Solution12 men and 18 boys working 712 hours a day can do a work in 60 days. If one man works equal to 2 boys, then the number of boys required to help 21 men to do twice the work in 50 days working 9 hours a day will be:
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution