Doubtnut Promotions Sticky

If 4 men or 5 women can construct a will in 82 days, the how long will it take for 5 men and 4 women to do the same work?

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we can follow these calculations:

Step 1: Determine the work done by men and women
Given that 4 men can complete the work in 82 days, we can find the total work in terms of man-days.

Total work = Number of men × Number of days = 4 men × 82 days = 328 man-days.

Similarly, for women, since 5 women can also complete the same work in 82 days:

Total work = Number of women × Number of days = 5 women × 82 days = 410 woman-days.

Step 2: Establish the relationship between men and women
From the above calculations, we can establish the relationship between the work done by men and women.

If 4 men = 5 women, then:
1 man = (5/4) women.

Step 3: Convert the work done by men into woman-days
Now, we can express the work done by men in terms of women.

Since 1 man = (5/4) women, then 5 men = 5 × (5/4) = 25/4 women.

Step 4: Calculate the total work done by 5 men and 4 women
Now we need to find out how much work 5 men and 4 women can do together.

Total work done by 5 men and 4 women in terms of women:
= (25/4) women + 4 women
= (25/4 + 16/4) women
= (41/4) women.

Step 5: Calculate the time taken by 5 men and 4 women to complete the work
Now, we know that the total work is equivalent to 410 woman-days.

To find the number of days taken by (41/4) women to complete the work, we can use the formula:

Time = Total Work / Work Rate.

Here, Total Work = 410 woman-days and Work Rate = (41/4) women.

Time = 410 / (41/4) = 410 × (4/41) = 40 days.

Final Answer
Thus, it will take 5 men and 4 women a total of 40 days to complete the work.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 5 men or 8 women can do a piece of work in 12 days, how many days will be taken by 2 men and 4 women to do the same work?

    A15 days
    B13 days
    C13 +1/3days
    D10 days
  • Question 2 - Select One

    If 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work ?

    A9 days
    B10 days
    C12 days
    D14 days
  • Question 3 - Select One

    If 3 men or 4 women can reap a field in 43 days, how long will 7 men and 5 women take to reap it?

    A7 days
    B11 days
    C12 days
    D16 days