If 'b' men can do a piece of work in 'c' days, then the number of days taken by 'd' men to do 1mth of the same piece of work be

A

bcd+m

B

bcdm

C

b+cd+m

D

b+cdm

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days 'd' men will take to complete 1mth of the work that 'b' men can complete in 'c' days. Let's break this down step by step.

1. Understand the Work Rate of 'b' Men:
- If 'b' men can complete the entire work in 'c' days, then the total work can be expressed in man-days as:
Total Work=b×c man-days

2. Calculate the Work Done by 'd' Men:
- The work done by 'd' men in one day is:
Work done by d men in one day=d man-days

3. Determine the Work to be Done:
- We are interested in 1mth of the total work. Therefore, the work to be done is:
Work to be done=1m×(b×c)=bcm man-days

4. Calculate the Number of Days Taken by 'd' Men:
- To find the number of days 'd' men take to complete bcm man-days of work, we use the formula:
Number of Days=Total WorkWork done per day=bcmd

5. Simplify the Expression:
- This simplifies to:
Number of Days=bcmd

Final Answer:
The number of days taken by 'd' men to do 1mth of the same piece of work is:
bcmd

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If m men can do a work in r days, then the number of days taken by (m+n) men to do it is :

    Am+nmn
    Bm+nmr
    Cmrm+n
    D(m+n)rmn
  • If m men can do a work in r days, then the number of days taken by (m+n) men do it is :

    Am+nmn
    Bm+nmr
    Cmrm+n
    D(m+n)rmn
  • If x men can do a work in z days. Then, the number of days taken by (x + y) men to do this is

    Axy(x+z)
    Bxz(x+y)
    C(z(x+y))/x
    Dx(x+y)z