If 'b' men can do a piece of work in 'c' days, then the number of days taken by 'd' men to do 1mth of the same piece of work be
bcd+m
bcdm
b+cd+m
b+cdm
The correct Answer is:B
To solve the problem, we need to determine how many days 'd' men will take to complete 1mth of the work that 'b' men can complete in 'c' days. Let's break this down step by step.
1. Understand the Work Rate of 'b' Men:
- If 'b' men can complete the entire work in 'c' days, then the total work can be expressed in man-days as:
Total Work=b×c man-days
2. Calculate the Work Done by 'd' Men:
- The work done by 'd' men in one day is:
Work done by d men in one day=d man-days
3. Determine the Work to be Done:
- We are interested in 1mth of the total work. Therefore, the work to be done is:
Work to be done=1m×(b×c)=bcm man-days
4. Calculate the Number of Days Taken by 'd' Men:
- To find the number of days 'd' men take to complete bcm man-days of work, we use the formula:
Number of Days=Total WorkWork done per day=bcmd
5. Simplify the Expression:
- This simplifies to:
Number of Days=bcmd
Final Answer:
The number of days taken by 'd' men to do 1mth of the same piece of work is:
bcmd
- If 'b' men can complete the entire work in 'c' days, then the total work can be expressed in man-days as:
Total Work=b×c man-days
- The work done by 'd' men in one day is:
Work done by d men in one day=d man-days
- We are interested in 1mth of the total work. Therefore, the work to be done is:
Work to be done=1m×(b×c)=bcm man-days
- To find the number of days 'd' men take to complete bcm man-days of work, we use the formula:
Number of Days=Total WorkWork done per day=bcmd
- This simplifies to:
Number of Days=bcmd
The number of days taken by 'd' men to do 1mth of the same piece of work is:
bcmd
Topper's Solved these Questions
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Question Bank - 13(b)
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- TIME AND WORK BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TIME AND WORK EXERCISE - Self Assessment Sheet - 13
15 Videos
- SIMPLE INTEREST BOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - SIMPLE INTEREST EXERCISE - Self Assessment Sheet
10 Videos
- TRIANGLESBOOK - S CHAND IIT JEE FOUNDATIONCHAPTER - TRIANGLESEXERCISE - Self Assessment Sheet - 18
10 Videos
Similar Questions
Knowledge Check
If m men can do a work in r days, then the number of days taken by (m+n) men to do it is :
Am+nmnBm+nmrCmrm+nD(m+n)rmnIf m men can do a work in r days, then the number of days taken by (m+n) men do it is :
Am+nmnBm+nmrCmrm+nD(m+n)rmnIf x men can do a work in z days. Then, the number of days taken by (x + y) men to do this is
Axy(x+z)Bxz(x+y)C(z(x+y))/xDx(x+y)z
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf x men can do a work in z days. Then, the number of days taken by (x + y) men to do this is
View SolutionIf x men can do a piece of work In x days, then the number of days in which y men can do the same work is
View SolutionIf 45 men can do a piece of work in 49 days, in how many days will 35 men do it?
View SolutionA can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?
View Solution