Doubtnut Promotions Sticky

M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)

A

18910

B

19

C

1835

D

18310

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A


Part of the job completed (by M) on the first day =118
Part of the job completed (by N) on the second day =120
Part of the job completed on the first 18 days =118+120=19180
Part of the job completed on the first 18 days . 182(19180)=1920
Remaining part =120
M work on the 19th day. He can complete the remaining part in 120118days=910 days.
Total time taken =18910 days

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82
  • Question 2 - Select One

    M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82
  • Question 3 - Select One

    M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

    A88
    B84
    C96
    D82