A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
The correct Answer is: days
To solve the problem step by step, we will first determine the work efficiencies of A and B, then calculate how much work they complete in a cycle of two days, and finally determine how many days it will take to complete the work.
1. Determine the Work Efficiency of A and B:
- A can complete the work in 30 days. Therefore, A's work efficiency is:
Efficiency of A=1 unit of work30 days=130 units per day
- B can complete the work in 10 days. Therefore, B's work efficiency is:
Efficiency of B=1 unit of work10 days=110 units per day
2. Calculate the Total Work:
- We can assume the total work to be the least common multiple (LCM) of the days taken by A and B to complete the work. The LCM of 30 and 10 is 30 units of work.
3. Calculate the Work Done in Two Days:
- In the first day, A works and completes:
Work done by A in 1 day=130 units
- In the second day, B works and completes:
Work done by B in 1 day=110 units
- Therefore, in two days, the total work done is:
Total work in 2 days=130+110=130+330=430=215 units
4. Calculate the Number of Two-Day Cycles to Complete the Work:
- To find out how many two-day cycles are needed to complete 30 units of work, we set up the equation:
Number of cycles=30 units215 units per 2 days=30×152=225 cycles
- This means it takes 225 two-day cycles to complete the work.
5. Calculate the Total Days Taken:
- Since each cycle takes 2 days, the total number of days taken to complete the work is:
Total days=225×2=450 days
6. Final Adjustment for Remaining Work:
- After 225 cycles, A will start again on the 451st day. Since they only need to complete 1 more unit of work, A will complete this in:
Days needed=1 unit×30 days/unit=130 days
- Therefore, the total time taken is:
450+130 days
Final Answer:
The total time taken to complete the work is approximately 450.03 days.
- A can complete the work in 30 days. Therefore, A's work efficiency is:
Efficiency of A=1 unit of work30 days=130 units per day
- B can complete the work in 10 days. Therefore, B's work efficiency is:
Efficiency of B=1 unit of work10 days=110 units per day
- We can assume the total work to be the least common multiple (LCM) of the days taken by A and B to complete the work. The LCM of 30 and 10 is 30 units of work.
- In the first day, A works and completes:
Work done by A in 1 day=130 units
- In the second day, B works and completes:
Work done by B in 1 day=110 units
- Therefore, in two days, the total work done is:
Total work in 2 days=130+110=130+330=430=215 units
- To find out how many two-day cycles are needed to complete 30 units of work, we set up the equation:
Number of cycles=30 units215 units per 2 days=30×152=225 cycles
- This means it takes 225 two-day cycles to complete the work.
- Since each cycle takes 2 days, the total number of days taken to complete the work is:
Total days=225×2=450 days
- After 225 cycles, A will start again on the 451st day. Since they only need to complete 1 more unit of work, A will complete this in:
Days needed=1 unit×30 days/unit=130 days
- Therefore, the total time taken is:
450+130 days
The total time taken to complete the work is approximately 450.03 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)33videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)30videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
Similar Questions
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionVianay and Vikram can complete a work in 48 and 36 days, respectively . If they work on alternate days beginning with Vinay, in how many days will the work be completed?
View Solution
Knowledge Check
- Question 1 - Select One
Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C40D50 - Question 2 - Select One
Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C40D50 - Question 3 - Select One
Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A45B35C49D50
A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?
View SolutionA and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionP and Q can do piece of work in 10 days in 10 days and 35 days. Respectively. If they work on alternate days begnining wit Q, in how may will the work be completed?
View SolutionChandni and Divakar can do a piece of work in 9 days and 12 days respectively. If they work for a day alternatively, Chandni beginning, in how many days, the work will be completed?
View Solution