Doubtnut Promotions Sticky

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is: 16 1 3 days


To solve the problem step by step, we will first determine the work efficiencies of A and B, then calculate how much work they complete in a cycle of two days, and finally determine how many days it will take to complete the work.

1. Determine the Work Efficiency of A and B:
- A can complete the work in 30 days. Therefore, A's work efficiency is:
Efficiency of A=1 unit of work30 days=130 units per day
- B can complete the work in 10 days. Therefore, B's work efficiency is:
Efficiency of B=1 unit of work10 days=110 units per day

2. Calculate the Total Work:
- We can assume the total work to be the least common multiple (LCM) of the days taken by A and B to complete the work. The LCM of 30 and 10 is 30 units of work.

3. Calculate the Work Done in Two Days:
- In the first day, A works and completes:
Work done by A in 1 day=130 units
- In the second day, B works and completes:
Work done by B in 1 day=110 units
- Therefore, in two days, the total work done is:
Total work in 2 days=130+110=130+330=430=215 units

4. Calculate the Number of Two-Day Cycles to Complete the Work:
- To find out how many two-day cycles are needed to complete 30 units of work, we set up the equation:
Number of cycles=30 units215 units per 2 days=30×152=225 cycles
- This means it takes 225 two-day cycles to complete the work.

5. Calculate the Total Days Taken:
- Since each cycle takes 2 days, the total number of days taken to complete the work is:
Total days=225×2=450 days

6. Final Adjustment for Remaining Work:
- After 225 cycles, A will start again on the 451st day. Since they only need to complete 1 more unit of work, A will complete this in:
Days needed=1 unit×30 days/unit=130 days
- Therefore, the total time taken is:
450+130 days

Final Answer:
The total time taken to complete the work is approximately 450.03 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?

    A45
    B35
    C40
    D50
  • Question 2 - Select One

    Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?

    A45
    B35
    C40
    D50
  • Question 3 - Select One

    Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?

    A45
    B35
    C49
    D50