The efficiency of A, B and C is the same. They started working on a certain job. After 5 days a leaves, after 5 moere days B leaves and C completes the remaining work in 5 more days. Find the time taken by eahc of them alone to complete the job. (in days)?
20
30
40
45
The correct Answer is:B
Let us assume that each of A, B and C alone can do in x-axis 15 days
A works for 5 days, B works for 10 days and C works 15 days.
∴5x+10x+15x=1
30x=1⇒=30
Topper's Solved these Questions
Similar Questions
P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)
View SolutionA can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.
View Solution
Knowledge Check
Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:
A60B54C72D90A, B and C together can do a piece of work in 40 days. After working with B and C for 16 days, A leaves and then B and C complete the remaining work in 40 days more. A alone could do the work in
A80 daysB90 daysC100 daysD120 daysA can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.
A6 daysB5 daysC8 daysD10 days
A can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.
View SolutionA can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.
View SolutionA and C started doing a work . After working for 6 days , both left and B alone completed the remaining work in 4 days .In how many days can C alone complete a work in 2 days , then in how many days can A alone complete the work ?
View SolutionA can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
View Solution