Doubtnut Promotions Sticky

To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how long A, B, and C would take to complete the work individually based on the relationships given in the question. Let's break down the solution step by step.

Step 1: Define Variables
Let:
- A's time to complete the work alone = x days
- B's time to complete the work alone = y days
- C's time to complete the work alone = z days

Step 2: Establish Relationships
From the problem, we have the following relationships:
1. C takes twice as long as A and B together:
z=211x+1y
This simplifies to:
z=2xyx+y

2. A takes three times as long as B and C together:
x=311y+1z
This simplifies to:
x=3yzy+z

3. A, B, and C together can complete the work in 5 days:
1x+1y+1z=15

Step 3: Substitute and Solve
Now we can substitute z in terms of x and y into the equation for A's time:
From the first relationship, we have:
z=2xyx+y
Substituting this into the second relationship:
x=3y2xyx+yy+2xyx+y=32xy2y(x+y)+2xy=6xy2y(x+y)+2xy

Step 4: Combine Equations
Now we have:
1x+1y+12xyx+y=15
This can be simplified to:
1x+1y+x+y2xy=15

Step 5: Solve the Equation
Multiply through by 10xy to eliminate the denominators:
10y+10x+5(x+y)=2xy
This simplifies to:
15x+15y=2xy
Rearranging gives:
2xy15x15y=0

Step 6: Factor the Quadratic
This can be factored as:
(2x15)(y15)=225
Let’s assume x=15 and solve for y:
(2(15)15)(y15)=225
This gives:
15(y15)=225y15=15y=30

Step 7: Find C's Time
Now substituting x=15 and y=30 back into the equation for z:
z=2xyx+y=2(15)(30)15+30=90045=20

Final Answer
Thus, the individual times to complete the work are:
- A = 15 days
- B = 30 days
- C = 20 days

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?

    A18 days
    B24 days
    C16 days
    D20 days
  • Question 2 - Select One

    A and B together can complete a work in 8 days and B and C together in 12 days. All of the three together can complete the work in 6 days. In how much time will A and C together complete the work?

    A8 days
    B10 days
    C12 days
    D20 days
  • Question 3 - Select One

    To do a certain work, B would take time thrice as long as A and C together and C twice as long as A and B together. The three men together complete the work in 10 days. The time taken by A to complete the work separately is

    A22 days
    B24 days
    C30 days
    D20 days