Work done by A in 3 days is equal to the work done by B in 4 days. What is the ratio of time taken by A and B to complete a work?
The correct Answer is:3:4
To solve the problem, we need to find the ratio of the time taken by A and B to complete a work based on the information given.
1. Understanding Work Done:
The work done by a person can be expressed as:
Work Done=Efficiency×Time
2. Setting Up the Equation:
According to the problem, the work done by A in 3 days is equal to the work done by B in 4 days. We can express this mathematically as:
Efficiency of A×3=Efficiency of B×4
3. Expressing Efficiency:
Let's denote the efficiency of A as EA and the efficiency of B as EB. Thus, we can rewrite the equation as:
EA×3=EB×4
4. Finding the Ratio of Efficiencies:
Rearranging the equation gives us:
EAEB=43
This means that A is more efficient than B.
5. Finding the Ratio of Time Taken:
The time taken to complete the work is inversely proportional to efficiency. Therefore, we can express the ratio of time taken by A and B as:
Time taken by ATime taken by B=EBEA
Substituting the values we found:
Time taken by ATime taken by B=34
6. Final Ratio:
Thus, the ratio of time taken by A and B to complete the work is:
Time taken by A : Time taken by B=3:4
Final Answer:
The ratio of time taken by A and B to complete the work is 3 : 4.
---
The work done by a person can be expressed as:
Work Done=Efficiency×Time
According to the problem, the work done by A in 3 days is equal to the work done by B in 4 days. We can express this mathematically as:
Efficiency of A×3=Efficiency of B×4
Let's denote the efficiency of A as EA and the efficiency of B as EB. Thus, we can rewrite the equation as:
EA×3=EB×4
Rearranging the equation gives us:
EAEB=43
This means that A is more efficient than B.
The time taken to complete the work is inversely proportional to efficiency. Therefore, we can express the ratio of time taken by A and B as:
Time taken by ATime taken by B=EBEA
Substituting the values we found:
Time taken by ATime taken by B=34
Thus, the ratio of time taken by A and B to complete the work is:
Time taken by A : Time taken by B=3:4
The ratio of time taken by A and B to complete the work is 3 : 4.
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 2
19 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
View SolutionWork done by (x+4) mean in (x+5) days is equal to the work done by (x-5) men in (x+20) days. What is the value of x?
View Solution
Knowledge Check
Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?
A20 daysB25 daysC30 daysD40 daysA and B work together to complete the rest of a job in 7 days. However, 37100 of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?
A20B25C30D10The work done by 2 men in a day is equal to the work done by 3 children in a day. The work done by 3 men in a day is equal to the work done by 5 women in a day. It takes 10 days for a man, a woman and a child to complete a job working together. How many days will 2 children working together take to complete the same job?
A30B15C17D34
Work done by A in one day is half of the work done by B in one day. Work done by B is half of the work done by C in one day. If C alone can complete the work .in 7 days, in how many days can A, B and C together complete the work? a. 4 b. 14 c. 21 d. 28 e. none of these
View SolutionA, B and C working together can finish certain piece of work in 28 days. They work together for 18 days, then B left. If rest work done by A and C in 25 days. Work done by A in 2 days is equal to work done by C in 3 days, then find in how many days A, B and C working alone will finish the work?
View SolutionA, B and C working together can finish a piece of work in 32 days. They worked for 24 days and after that the C left. Rest of the work is completed by A and B in 28 days. Work done by A in 1 day is equal to work done by B in 2 days. In how many days working alone each one will finish the work?
View Solution10 men and 8 women together can complete a work in 5 days. Work done by one woman in a day is equal to half the work done by a man in 1 day. How many days will it take for 4 men and 6 women to complete that work?
View Solution10 men and 8 women can together complete a work in 5 days. Work done by a woman is equal to the half of the work done by a man. In how many days, will 4 men and 6 women complete that work ?
View Solution