Work done by A in 3 days is equal to the work done by B in 4 days. What is the ratio of time taken by A and B to complete a work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:3:4


To solve the problem, we need to find the ratio of the time taken by A and B to complete a work based on the information given.

1. Understanding Work Done:
The work done by a person can be expressed as:
Work Done=Efficiency×Time

2. Setting Up the Equation:
According to the problem, the work done by A in 3 days is equal to the work done by B in 4 days. We can express this mathematically as:
Efficiency of A×3=Efficiency of B×4

3. Expressing Efficiency:
Let's denote the efficiency of A as EA and the efficiency of B as EB. Thus, we can rewrite the equation as:
EA×3=EB×4

4. Finding the Ratio of Efficiencies:
Rearranging the equation gives us:
EAEB=43
This means that A is more efficient than B.

5. Finding the Ratio of Time Taken:
The time taken to complete the work is inversely proportional to efficiency. Therefore, we can express the ratio of time taken by A and B as:
Time taken by ATime taken by B=EBEA
Substituting the values we found:
Time taken by ATime taken by B=34

6. Final Ratio:
Thus, the ratio of time taken by A and B to complete the work is:
Time taken by A : Time taken by B=3:4

Final Answer:
The ratio of time taken by A and B to complete the work is 3 : 4.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Three workers A, B and C working together completed a job in 10 days. However, C only worked for the first three days when 37% of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the worker C to complete the entire work?

    A20 days
    B25 days
    C30 days
    D40 days
  • A and B work together to complete the rest of a job in 7 days. However, 37100 of the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

    A20
    B25
    C30
    D10
  • The work done by 2 men in a day is equal to the work done by 3 children in a day. The work done by 3 men in a day is equal to the work done by 5 women in a day. It takes 10 days for a man, a woman and a child to complete a job working together. How many days will 2 children working together take to complete the same job?

    A30
    B15
    C17
    D34