X works four times as fast as Y.Y takes 60 days more than X to complete a job. Find the time in which X and Y working together can complete the job ( in days)
20
10
16
12
The correct Answer is:C
Let the time in which X and Y can complete the job be x days days y repectively.
1x=4(1y) (1)
y=x+60 (2)
From Eq. (1), we get
y=4x
Substituting this value in Eq. (2) ,we get
4x=x=60
x=20
y=80
The time in which X and Y can complete the job (in days) =xyx+y=16
Topper's Solved these Questions
Similar Questions
X works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View SolutionX works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View Solution
Knowledge Check
- Question 1 - Select One
A work three times as fast as B.B takes 56 days more than A to complete a work. Working together in how days can they complete the work?
A24B21C27D29 - Question 2 - Select One
Five men or ten women can complete a job in 20 days. Find the time in which four men and four women can complete it (in days)
A15B20C1313D1623 - Question 3 - Select One
Y is thrice as efficient as Z who is half as efficient as X,X,Y and Z can complete a job in 25 days. Find the time in which X and Y can complete it (in days)
A30B36C40D45
A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionB takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.
View SolutionA takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution