Class 7 | MATHS |
Chapter | TIME AND WORK |
S CHAND IIT JEE FOUNDATION | Question Bank - 13(a) |
Number Of Questions | 30 |
Academic Year | 2023-24 |
A and B together can complete a piece of work in 16 days while B and C together can complete the same work in 12 days and A and C together in 24 days. Find out the number of days that A will take to compete the work, working alone.
A and B together can do a piece of work in 8 days. B alone can do it in 12 days. B alone works at it for 4 days. In how many more days after that could A alone complete it.
A man and a boy can do a piece of work in 24 days. If the man works alone for last 4 days, it is complete in 5 days. How long would the boy take to do it alone ?
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? `18\ d a y s` b. `\ 24\ d a y s` c. `30\ d a y s` d. `36\ d a y s`
A and B can do a job together in 7 days. A is `1 3/4` times as efficient as B. the same job can be done by A alone in: `9 1/3d a y s` b. `11\ d a y s` c. `12 1/4` d. `16 1/3\ d a y s`
I can do a piece of work in 8 days, which can be done by you in 10 days How long would it take to do it if we work together ?
X is twice as good as a workman as Y. X finished a piece of work in 3 hours less than Y. In how many hours could they have finished that piece of work together ?
A can cultivate `2/5` the of a land in 6 days and B can cultivate `1/3` rd of the same land in 10 days. Working together A and B can cultivate `4/5`the of the land in
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
A , B and C can do a piece of work in 11 days, 20 days and 55 days respectively, working alone. How soon can the work be done if A is assisted by B and C on alternate days?
A can do a piece of work in 20 days and B in 40 days. A begins the work and there after they work alternately one on each day. One which day will the work be completed ?
A can complete a work in 9 days, B in 10 days and C in 15 days. B and C together started the work but left the work after 2 days. The time taken to complete the remaining work by A will be
A can do a piece of work in 4 hours, B and C together in 3 hours, and A and C together in 2 hours. How long will B alone take to do it? `8\ hou r s` b. `10\ hou r s` c. `12\ hou r s` d. `24\ hou r s`
Ram can do a piece of work in 6 days and Shyam can finish the same work in 12 days. How much work will be finished if both work together for 2 days ?
A is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
A does half as much work as B in one-sixth of the time.If together they take 10 days to complete a work,how much time shall B alone take to do it?
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
A man and a boy received 800 as wages for 5 days for the work they did together. The man's efficiency in the work was three times that of the boy. What are the daily wages of the boy? `R s .40` b. `R s .44` c. `R s .56` d. `R s .76`
a certain number of persons can complete a piece of work in 55 days. If there were 6 persons more the work could be finished in 11 days less. How many persons were originally there ?
A can complete a work in 18 days, B can do the same work in half the time as A. What part of work can be completed by both of them working together in 1 day
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed? `4` b. `15` c. `7` d. `8`
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? `110\ d a y s` b. `11\ d a y s` c. `15\ d a y s` d. `20\ d a y s`
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? `12\ d a y s` b. `15\ d a y s` c. `16\ d a y s` d. `18\ d a y s`
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? `5 5/(11)` b. `5 6/(11)` c. `6 6/(11)` d. `6 6/(11)`
If 'b' men can do a piece of work in 'c' days, then the number of days taken by 'd' men to do `(1)/(m)`th of the same piece of work be
If 16 men or 20 women can do a piece of work in 25 days, in what time will 28 men and 15 women do it ?
If one man or two women or three boys can do a piece of work in 22 days, then the same piece of work will be done by 1 man, 1 boy and 1 women in
A does half as much work as B in three-fourth of the time. If together they take 18 days to complete a work, how much time shall B take to do it alone ?
A man completes `5/8` of a job in 10 days. At this rate, how many more days will it take him to finish the job? `5` b. `6` c. `7` d. `7 1/2`
10 men and 15 women finish a work in 6 days. One man alone finishes that work in 100 days. In how many days will a women finish the work ?
Question Bank - 13(a) questions and complete solutions for chapter TIME AND WORK of S CHAND IIT JEE FOUNDATION of Class 7