Class 9 | MATHS |
Chapter | TIME AND WORK |
PEARSON IIT JEE FOUNDATION | TEST YOUR CONCEPTS |
Number Of Questions | 50 |
Academic Year | 2023-24 |
A can read a book in x minutes . What part of the boon can he read in k minutes?
Work done by A in 3 days is equal to the work done by B in 4 days. What is the ratio of time taken by A and B to complete a work?
A can complete `(2)/(3)` of work in 6 days. In what time can he complete `(4)/(9)` of the work ?
A can do a work in x days and B can do the same work in y days. If `xgty` , then who can do more work in 6 days?
If x men can do a work in y days, then a man can do the same work in 2y days. (True/False)
A is twice as good workman as B.A takes 6 days the complete a work. In what time can B complete the work?
A and B together can do work in 20 days, B and and C and do the same work in 60 days. Who is the most efficient among A,B and C?
A and B the completed work and divided the earings in the ratio of `2:3`. What is the ratio of time taken to complete the work by A and B, respectively?
8 men can knit 8 baskets in 8 days. In how many days cam 3 m en knit 3 baskets?
A man can load one box in 9 minutes. A truck can contain 8 boxes. If 16 men load for one and a half hour, how many trucks will be loaded?
Pipe A can fill a tank in 40 minutes . Pies B can empty the tank in 30 minutes . If both the pipes are opened simultaneously when tank is half full, then will be tank become full or empty?
Pipe A can fill a tank in 2 hours at the rate of the 6 litres per minute. What is the capacity of the tank?
If A and B cadn do a work in x and y days, respectively, then time taken by A and B together to complete the work is `(x+y)/2`` (True/False)
A can do a task in 18 days. He works for 10 days and leaves. The remaining workin completed by B adn C. If they get Rs. 9000 for completing the work, then who receives more share in the earings?
12 men or 18 woman can do a work in 16 days. In how many days 12 men and 18 woman can do the work?
A, B and C can do a work in x,3x and 5x days, respectively. They worked together and earned Rs. 460. What is the share of B?
A and B can do a work in 20 and 30 days, respectiveyl .They completed the work in 10 days with the help of C. In how days can C alone do the work?
A can point 6 walls in 5 days. B can point 8 walls (of the same area) in 4 days. Working together, in hown many days can they point 48 walls (of the same area)?
The ratio of efficienciess of A, B can C is `2:3:4`. Working together, they can coplete a work in 20 days. In how many days can C alone finish the work?
On working 10 hourse a day, 15 men can complete a piece of work in 20 days. In how many days can 30 men complete if they work 5 hours per day?
A and B can do a work in 20 days, B and C in 40 days and A and C in 30 days. Who is the most efficient among the the three perosn?
A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
Work done by (x+4) mean in (x+5) days is equal to the work done by (x-5) men in (x+20) days. What is the value of x?
Pipe A in fill a tank in 15 horurs Pipe A and Pipe B together can fill it in 10 hours Pipe B can fill 8 liters per minute. Find the capicity of the tank
18 men can construct 200 m long wall in 16 days working 9 hours per day. In how many days can 36men construct 500 m long wall working 6 hours per day?
Vianay and Vikram can complete a work in 48 and 36 days, respectively . If they work on alternate days beginning with Vinay, in how many days will the work be completed?
A is twice as efficient as B. Time taken by B to complete `(4)/(7)` part of the work is 6n days more than the time taken by A to complete `(3)/(7)` part of the same work. In how many days can A alone do the work?
The ratio of work efficiency of a man and a woman is `3:2`. A woman can do a work in 30 days. In how many can 4 men and 4 women do the work?
12 men of 15 women can do a work in 40 days. 8 men and 10 women can do the work in how many days?
12 men and 15 women can do a work in 6 days, and 6 men and 12 women can do it in 10 days, in how many days can 8 men and 10 women do the same work?
Certain sum is sufficient to pay wage to A for 15 days or to B for 30 days. For how many days is the sum sufficient to pay both A and B?
A,B and C can do a work in 20,25 and 30, respectively. They together started the work, but B adn A left the work 7 days and 4 days, respectively before completion of the work. How many days did C work for?
Anand is 50% more efficient than Bharath and Bharath is 100% more efficient that Chandu. Working together, they can complete a work in 10 days. In how many days can Anand alone do the work?
300 men can construct a200m long wall in 12 days working 8 hours a day. In how many days can 120 men construct 180 m long wall working 9 hours per day?
A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)
Thirty men can dig a well in 10 days on working 8 hours a day. They started the work but after 2 days, 10 men left. How many hours a day should the remaining men work to complete it on time?
Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
A certain number of men completed a job in 10 days. If there 5 more men, it could have been completd in 8 days. How many men will be required to complete it ?
Two pipes A and B can fill a tank in 20 and 24 minutes. Resepctively. Pipe C can empty the tank in 10 minutes. Pipes A and B are opened for 5 minutes and then pipe C is also opend. In what time can tank become full or empty after opening pipe C?
a can complete a piece of work in 15 days. B can complete it in 10 days. With the help C, they can complete it in 4 days. They all worked togther and earned a total of s. 750. Find C's share.
Time taken by 8 men and 6 boys is 3 times the time taken 15 men and 30 boys to complete a world if. 8 men and 12 boys can do a work in 34 days. Then how many men can do in 17 days?
Prakash, Rohit and Sameer cam complete a job in 1 days, 20 days, adn 10 days, respectively. They sarted the job but Prakash was unwell on the first day, he could not work at his full capacity and Prakash left after a day. The other two completed the job. Rohit was pair Rs. 17,000 out of the total of Rs. 60,000 paid to them. At what percentage of his full capicity, did Prakash work on the first day ?
Pipe A and pipe B can fill a tank in 24 minutes and 28 minutes , respectively. IF both the pipes are opened simultaneously, then after how many minues. Should pipe B be closed such that the tank becomes full in 18 minuts ?
In a group, there were M men. They sarted working on a job of 330 units. Each man could do 1 units in 1 day. After each day of wark, a man of the sam efficiency as each man in the group in he group. The job was completed at the end of 11 days. Find M
Ram and Shyam can complete a job in 20 days. If they work together. If they complete it by working on elternate days, in how many days will it be completed?
A,B and C can complete a job in 20 days, 30 days, and 40 days, respectively. They worked for 6 days and then A left. B and C completed the job. Find B's wages in the total wages of Rs. 20,000 paid to them ( in Rs.)
10 women can complete a job in 12 days . 4 of them started working on the job. After every 4 days, a women joined the group. Every woman joinin the group has equal capcity as any woman in the group. Find the time taken to complete the job ( In days)
Prakash, Ramesh and Suresh started a job. After 2 days, Prakash left. After another 2 days, Ramesh left. In another 2 days. Suresh completed the reaminin part of the job . If Prakash can complete the same work in more than 6 days, and Ramesh can complete it in more than 12 days, who got the highest share of the wages?
TEST YOUR CONCEPTS questions and complete solutions for chapter TIME AND WORK of PEARSON IIT JEE FOUNDATION of Class 9