A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?
To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information given.
Step 1: Determine Work Rates
1. A and B together can finish the work in 12 days.
- Therefore, their combined work rate is 112 of the work per day.
- This means A+B=112.
2. B and C together can finish the work in 16 days.
- Therefore, their combined work rate is 116 of the work per day.
- This means B+C=116.
Step 2: Calculate Work Done by A, B, and C
3. A works alone for 5 days:
- Let the work done by A in one day be a.
- In 5 days, A does 5a.
4. B works alone for 7 days:
- Let the work done by B in one day be b.
- In 7 days, B does 7b.
5. C works alone for 13 days:
- Let the work done by C in one day be c.
- In 13 days, C does 13c.
Step 3: Set Up the Equation
6. The total work done by A, B, and C combined equals 1 (the whole work):
5a+7b+13c=1
Step 4: Substitute Work Rates
7. From the equations A+B=112 and B+C=116, we can express a and c in terms of b:
- From A+B=112, we have a=112−b.
- From B+C=116, we have c=116−b.
Step 5: Substitute into Total Work Equation
8. Substitute a and c into the total work equation:
5(112−b)+7b+13(116−b)=1
Expanding this gives:
512−5b+7b+1316−13b=1
Combine like terms:
512+1316−11b=1
Step 6: Find a Common Denominator and Solve for b
9. The common denominator for 12 and 16 is 48. Convert the fractions:
- 512=2048
- 1316=3948
- Thus, 2048+3948−11b=1
- Combine the fractions:
5948−11b=1
Rearranging gives:
11b=5948−1=5948−4848=1148
Therefore:
b=1148×11=148
Step 7: Find a and c
10. Now substitute b back to find a and c:
- a=112−148=448−148=348=116
- c=116−148=348−148=248=124
Step 8: Calculate Days for C Alone
11. Since c=124, C can finish the work alone in 24 days.
Final Answer
C alone can finish the complete work in 24 days.
1. A and B together can finish the work in 12 days.
- Therefore, their combined work rate is 112 of the work per day.
- This means A+B=112.
- Therefore, their combined work rate is 116 of the work per day.
- This means B+C=116.
3. A works alone for 5 days:
- Let the work done by A in one day be a.
- In 5 days, A does 5a.
- Let the work done by B in one day be b.
- In 7 days, B does 7b.
- Let the work done by C in one day be c.
- In 13 days, C does 13c.
6. The total work done by A, B, and C combined equals 1 (the whole work):
5a+7b+13c=1
7. From the equations A+B=112 and B+C=116, we can express a and c in terms of b:
- From A+B=112, we have a=112−b.
- From B+C=116, we have c=116−b.
8. Substitute a and c into the total work equation:
5(112−b)+7b+13(116−b)=1
Expanding this gives:
512−5b+7b+1316−13b=1
Combine like terms:
512+1316−11b=1
9. The common denominator for 12 and 16 is 48. Convert the fractions:
- 512=2048
- 1316=3948
- Thus, 2048+3948−11b=1
- Combine the fractions:
5948−11b=1
Rearranging gives:
11b=5948−1=5948−4848=1148
Therefore:
b=1148×11=148
10. Now substitute b back to find a and c:
- a=112−148=448−148=348=116
- c=116−148=348−148=248=124
11. Since c=124, C can finish the work alone in 24 days.
C alone can finish the complete work in 24 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 130videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
(A + B) working together can finish certain piece of work in 8 days and (B + C) can finish it in 12 days. If A works for 4 days and B works for 7 days, rest work is done by C in 9 days. In how many days C will finish the work working alone?
View SolutionA and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
View Solution
Knowledge Check
- Question 1 - Select One
A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
A48B60C24D30 - Question 2 - Select One
A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?
A60 daysB36 daysC45 daysD24 days - Question 3 - Select One or More
A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?
A24B18C36D42
A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?
View SolutionA can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
View SolutionA and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?
View SolutionA and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View Solution