Doubtnut Promotions Sticky

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will first determine the work rates of A, B, and C based on the information given.

Step 1: Determine Work Rates
1. A and B together can finish the work in 12 days.
- Therefore, their combined work rate is 112 of the work per day.
- This means A+B=112.

2. B and C together can finish the work in 16 days.
- Therefore, their combined work rate is 116 of the work per day.
- This means B+C=116.

Step 2: Calculate Work Done by A, B, and C
3. A works alone for 5 days:
- Let the work done by A in one day be a.
- In 5 days, A does 5a.

4. B works alone for 7 days:
- Let the work done by B in one day be b.
- In 7 days, B does 7b.

5. C works alone for 13 days:
- Let the work done by C in one day be c.
- In 13 days, C does 13c.

Step 3: Set Up the Equation
6. The total work done by A, B, and C combined equals 1 (the whole work):
5a+7b+13c=1

Step 4: Substitute Work Rates
7. From the equations A+B=112 and B+C=116, we can express a and c in terms of b:
- From A+B=112, we have a=112b.
- From B+C=116, we have c=116b.

Step 5: Substitute into Total Work Equation
8. Substitute a and c into the total work equation:
5(112b)+7b+13(116b)=1
Expanding this gives:
5125b+7b+131613b=1
Combine like terms:
512+131611b=1

Step 6: Find a Common Denominator and Solve for b
9. The common denominator for 12 and 16 is 48. Convert the fractions:
- 512=2048
- 1316=3948
- Thus, 2048+394811b=1
- Combine the fractions:
594811b=1
Rearranging gives:
11b=59481=59484848=1148
Therefore:
b=1148×11=148

Step 7: Find a and c
10. Now substitute b back to find a and c:
- a=112148=448148=348=116
- c=116148=348148=248=124

Step 8: Calculate Days for C Alone
11. Since c=124, C can finish the work alone in 24 days.

Final Answer
C alone can finish the complete work in 24 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can complete a work in 12 days and B and C can do it in 16 days. A work for 5 days and B for 7 days then C complete the remaining work in 13 days. In how many days B can finish the work?

    A48
    B60
    C24
    D30
  • Question 2 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 3 - Select One or More

    A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

    A24
    B18
    C36
    D42