A,B and C can do a work in 20,25 and 30, respectively. They together started the work, but B adn A left the work 7 days and 4 days, respectively before completion of the work. How many days did C work for?
The correct Answer is:12
To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate how many days C worked for.
Step 1: Determine the work rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 25 days, so B's work rate is 125 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
Step 2: Set up the equation for total work done
Let the total number of days taken to complete the work be x.
- A works for x−4 days (since A leaves 4 days before completion).
- B works for x−7 days (since B leaves 7 days before completion).
- C works for all x days.
The equation for the total work done can be expressed as:
(120)(x−4)+(125)(x−7)+(130)(x)=1
Step 3: Find a common denominator
The least common multiple (LCM) of 20, 25, and 30 is 300. We will multiply the entire equation by 300 to eliminate the fractions:
300(120)(x−4)+300(125)(x−7)+300(130)(x)=300
This simplifies to:
15(x−4)+12(x−7)+10x=300
Step 4: Expand and simplify the equation
Expanding the equation gives:
15x−60+12x−84+10x=300
Combining like terms:
(15x+12x+10x)−144=300
37x−144=300
Step 5: Solve for x
Adding 144 to both sides:
37x=444
Dividing by 37:
x=44437=12
Step 6: Calculate how many days C worked
Since x=12, C worked for all 12 days.
Final Answer
C worked for 12 days.
---
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 25 days, so B's work rate is 125 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
Let the total number of days taken to complete the work be x.
- B works for x−7 days (since B leaves 7 days before completion).
- C works for all x days.
(120)(x−4)+(125)(x−7)+(130)(x)=1
The least common multiple (LCM) of 20, 25, and 30 is 300. We will multiply the entire equation by 300 to eliminate the fractions:
300(120)(x−4)+300(125)(x−7)+300(130)(x)=300
This simplifies to:
15(x−4)+12(x−7)+10x=300
Expanding the equation gives:
15x−60+12x−84+10x=300
Combining like terms:
(15x+12x+10x)−144=300
37x−144=300
Adding 144 to both sides:
37x=444
Dividing by 37:
x=44437=12
Since x=12, C worked for all 12 days.
C worked for 12 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 2
19 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
A10 daysB9 daysC12 daysD14 daysA, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can do a work in 12, 15 and 18 days respectively. They started the work together but A left after 2 days and B left the work 3 days before the competition of work. Find the number of days it took them to complete the work.
View SolutionA, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can do a piece of work in 20, 24 and 30 days respectively. All three of them began the work together but B left 3 days before completion of the work. In how many days was the work completed?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View Solution