A,B and C can do a work in 20,25 and 30, respectively. They together started the work, but B adn A left the work 7 days and 4 days, respectively before completion of the work. How many days did C work for?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:12


To solve the problem step by step, we will first determine the work done by A, B, and C, and then calculate how many days C worked for.

Step 1: Determine the work rates of A, B, and C
- A can complete the work in 20 days, so A's work rate is 120 of the work per day.
- B can complete the work in 25 days, so B's work rate is 125 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.

Step 2: Set up the equation for total work done
Let the total number of days taken to complete the work be x.

- A works for x4 days (since A leaves 4 days before completion).
- B works for x7 days (since B leaves 7 days before completion).
- C works for all x days.

The equation for the total work done can be expressed as:
(120)(x4)+(125)(x7)+(130)(x)=1

Step 3: Find a common denominator
The least common multiple (LCM) of 20, 25, and 30 is 300. We will multiply the entire equation by 300 to eliminate the fractions:
300(120)(x4)+300(125)(x7)+300(130)(x)=300
This simplifies to:
15(x4)+12(x7)+10x=300

Step 4: Expand and simplify the equation
Expanding the equation gives:
15x60+12x84+10x=300
Combining like terms:
(15x+12x+10x)144=300
37x144=300

Step 5: Solve for x
Adding 144 to both sides:
37x=444
Dividing by 37:
x=44437=12

Step 6: Calculate how many days C worked
Since x=12, C worked for all 12 days.

Final Answer
C worked for 12 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?

    A10 days
    B9 days
    C12 days
    D14 days
  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10