Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual
1 50
2 100
3 70
4 35
Answer : 2. "100" Explanation :Answer: B) 100 Explanation: Let the Efficienc
Related Solutions
Pavan is thrice as efficient as koushik. Pavan alone takes 30 days to complete a work. In how many days can koushik finish the same work?
View SolutionA and B working together can finish certain piece of work in 10 days. If A works at of his actual efficiency and B works at of his actual efficiency, then work will be completed in 9 days. If A works at of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished?
View Solution(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with half of his efficiency, then work will be completed in 4 days. In how many days will A and B do this work alone ?
View Solution(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?
View SolutionTwo workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require
View SolutionTwo workers A and B working together completed a job in 5
days. If A worked twice as efficiently as he actually did and
B worked 1/3 as efficiently as he actually did, the work would
have completed in 3 days. Fine the time for A to complete
the job alone.View SolutionBunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
View SolutionBunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
View SolutionA and B can finish a work in 10 days. If A is equal to its actual efficiency (2)/(3) works and B of its actual efficiency (5)/(3) works, the work is finished in 9 days. If A is equal to its actual efficiency (1)/(2) work and B doubles his original efficiency, in how many days will the work be finished?
View Solution(A+B) He can do a piece of work in 5 days. If A doubles his efficiency and B doubles his efficiency (1)/(3) then the work is completed in 3 days. In how many days will A complete the work?
View SolutionA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
View SolutionA and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with times of his efficiency, then in how many days working together work will be finished?
View SolutionTwo workers 'A' and 'B' working together completed a job in 5 days. Had 'A' worked twice as efficiently as he actually did, the work would have completed in 3 days. In how many days could 'A' alone complete the job ?
View SolutionA and B can do a piece of work in 4 days. If A decreases his efficiency by 30% and B increases his efficiency by 10%, then the work will be finished in 5 days. A to his true potential and B to his potential 1(1)/(2) Guna works if they both work together then in how many days will the work be finished?
View SolutionTwo workers A and B working together completed a job in 5 days. If A worked twice as efficient, as he actually did and B worked as efficiently as he actually did, the work would have been completed in 3 days. A alone could complete the work in b. c. d. none of these
View SolutionA is twice as efficient as B in doing the work and B is twice as efficient in the work as C. If A and B together can do a piece of work in 4 days, then in how many days will C alone complete it?
View SolutionRahul is twice efficient as Ram. If both of them can complete the work in 12 days. Then find the number of days Rahul would take to complete the work above.
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionHenry and Ford are two different persons, but when they work together, they complete it in 10 days. Had Henry worked at half of his efficient and Ford at five times of his efficiency it would have taken them to finish the job in of the scheduled time. In how many days can Ford complete the job working alone?
View Solution