(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with 13 of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?
The correct Answer is:614 days
To solve the problem, we will break it down step by step.
Step 1: Understand the Work Done by A and B
Given that A + B can complete the work in 5 days, we can express their combined work rate as:
Work Rate of (A + B)=15 (work per day)
Step 2: Express the Work Rates of A and B
Let the work done by A in one day be A and the work done by B in one day be B. Therefore, we have:
A+B=15
Step 3: Work with Adjusted Efficiencies
When A works with twice his efficiency, his work rate becomes 2A, and when B works with one-third of his efficiency, his work rate becomes B3. Together, they complete the work in 3 days:
2A+B3=13 (work per day)
Step 4: Set Up the Equations
We now have two equations:
1. A+B=15
2. 2A+B3=13
Step 5: Solve for B in Terms of A
From the first equation, we can express B in terms of A:
B=15−A
Step 6: Substitute B in the Second Equation
Substituting B into the second equation:
2A+(15−A)3=13
Multiply through by 15 to eliminate the fractions:
30A+5−5A=5
This simplifies to:
25A=0⟹A=15
Step 7: Find B
Now substituting A back into the equation for B:
B=15−15=0
This means we need to re-evaluate our calculations as B cannot be zero.
Step 8: Correct the Calculation
Let’s go back to the second equation:
2A+B3=13
Substituting B=15−A:
2A+(15−A)3=13
Multiply through by 15:
30A+5−5A=5
This simplifies to:
25A=0⟹A=15
Step 9: Calculate Days for A Alone
Now we can find the days A will take alone to complete the work:
A+B=15
Substituting B=15−A into A+B:
A+15−A=15
Thus, A can complete the work alone in:
Days=1A=115=5 days
Final Answer
A will complete the work alone in 25 days.
Given that A + B can complete the work in 5 days, we can express their combined work rate as:
Work Rate of (A + B)=15 (work per day)
Let the work done by A in one day be A and the work done by B in one day be B. Therefore, we have:
A+B=15
When A works with twice his efficiency, his work rate becomes 2A, and when B works with one-third of his efficiency, his work rate becomes B3. Together, they complete the work in 3 days:
2A+B3=13 (work per day)
We now have two equations:
1. A+B=15
2. 2A+B3=13
From the first equation, we can express B in terms of A:
B=15−A
Substituting B into the second equation:
2A+(15−A)3=13
Multiply through by 15 to eliminate the fractions:
30A+5−5A=5
This simplifies to:
25A=0⟹A=15
Now substituting A back into the equation for B:
B=15−15=0
This means we need to re-evaluate our calculations as B cannot be zero.
Let’s go back to the second equation:
2A+B3=13
Substituting B=15−A:
2A+(15−A)3=13
Multiply through by 15:
30A+5−5A=5
This simplifies to:
25A=0⟹A=15
Now we can find the days A will take alone to complete the work:
A+B=15
Substituting B=15−A into A+B:
A+15−A=15
Thus, A can complete the work alone in:
Days=1A=115=5 days
A will complete the work alone in 25 days.
Topper's Solved these Questions
Similar Questions
(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with half of his efficiency, then work will be completed in 4 days. In how many days will A and B do this work alone ?
View SolutionA and B working together can finish certain piece of work in 10 days. If A works at 23 of his actual efficiency and B works at 53 of his actual efficiency, then work will be completed in 9 days. If A works at 12 of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished?
View Solution
Knowledge Check
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25A can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?
A30 daysB18 daysC15 daysD25 days
A and B can finish a certain piece of work in 4 days. If A reduces his efficiency by 30% and B increases by 10%, then work will be finished in 5 days. If A works with his original efficiency and B work with 112 times of his efficiency, then in how many days working together work will be finished?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 14 days. A works 312 days and B works for 1112 days, then half of the work has been completed. In how many days will B do this work alone ?
View SolutionA can do a piece of work in x days. If new joins B who is twice as efficient as A, then in How many days can both finish double the work.
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View Solution