(A + B) can do a piece of work in 5 days. If A works with twice of his efficiency and B works with 13 of his efficiency, then work will be completed in 3 days. In how many days will A do this work alone ?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:614 days


To solve the problem, we will break it down step by step.

Step 1: Understand the Work Done by A and B
Given that A + B can complete the work in 5 days, we can express their combined work rate as:
Work Rate of (A + B)=15 (work per day)

Step 2: Express the Work Rates of A and B
Let the work done by A in one day be A and the work done by B in one day be B. Therefore, we have:
A+B=15

Step 3: Work with Adjusted Efficiencies
When A works with twice his efficiency, his work rate becomes 2A, and when B works with one-third of his efficiency, his work rate becomes B3. Together, they complete the work in 3 days:
2A+B3=13 (work per day)

Step 4: Set Up the Equations
We now have two equations:
1. A+B=15
2. 2A+B3=13

Step 5: Solve for B in Terms of A
From the first equation, we can express B in terms of A:
B=15A

Step 6: Substitute B in the Second Equation
Substituting B into the second equation:
2A+(15A)3=13
Multiply through by 15 to eliminate the fractions:
30A+55A=5
This simplifies to:
25A=0A=15

Step 7: Find B
Now substituting A back into the equation for B:
B=1515=0
This means we need to re-evaluate our calculations as B cannot be zero.

Step 8: Correct the Calculation
Let’s go back to the second equation:
2A+B3=13
Substituting B=15A:
2A+(15A)3=13
Multiply through by 15:
30A+55A=5
This simplifies to:
25A=0A=15

Step 9: Calculate Days for A Alone
Now we can find the days A will take alone to complete the work:
A+B=15
Substituting B=15A into A+B:
A+15A=15
Thus, A can complete the work alone in:
Days=1A=115=5 days

Final Answer
A will complete the work alone in 25 days.

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • A can do a piece of work in 40 days. B does the same work with 60% more efficiency. How many days will B take to complete the work alone?

    A30 days
    B18 days
    C15 days
    D25 days