Doubtnut Promotions Sticky

A and B working together can finish certain piece of work in 10 days. If A works at 23 of his actual efficiency and B works at 53 of his actual efficiency, then work will be completed in 9 days. If A works at 12 of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:847 days

|
Answer

Step by step video, text & image solution for A and B working together can finish certain piece of work in 10 days. If A works at (2)/(3) of his actual efficiency and B works at (5)/(3) of his actual efficiency, then work will be completed in 9 days. If A works at (1)/(2) of his actual efficiency and B works at double of his actual efficiency, then in how many days work will be finished? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?

    A813
    B8.5
    C9
    D12
  • Question 1 - Select One

    Two workers A and B working together completed a job in 5 days. If A worked twice as efficiently as he actually did and B worked 13 as efficiently as he actually did, the work would have been completed in 3 days. To complete the job alone. A would require

    A515 days
    B614 days
    C712 days
    D834 days
  • Question 1 - Select One

    Two workers A and B working together completed a job in 5
    days. If A worked twice as efficiently as he actually did and
    B worked 1/3 as efficiently as he actually did, the work would
    have completed in 3 days. Fine the time for A to complete
    the job alone.

    A614 days
    B534 days
    C5 days
    D3 days

Similar Questions