Doubtnut Promotions Sticky

Question

X can do a piece of work in 4 days. When he had worked for 4 days Y joined him. If complete work was finished in 16 days. Y can alone finish that worķ in: a 27 days b 36 days c 42 days d 18 days

Text Solution
Verified by Experts

Correct option b 36 days Explanation:According to the question X → 24 days ⇒work done by X in 4 days alone = 4×1=4units Remaining work = 24-4=20 units ⇒20 units done by both together in 16-4 days = 12 days ⇒Then efficiencies of X+Y


Related Solutions