Doubtnut Promotions Sticky

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Video Solution
|
Answer

Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Visitors to a show were charged Rs. 15 each on the first day, Rs. 7.50 on the second day, Rs. 2.50 on the third day and total attendance on three days were in the ratio 2 : 5 : 13 respectively. The average charge per person for the entire three days is

    ARs 5
    BRs 5.50
    CRs 6
    DRs 7
  • Question 2 - Select One

    The school canteen charges Rs 20 for lunch and Rs 4 for milk for each day. How much money do you spend in 5 days on these things?

    A140
    B120
    C105
    D115
  • Question 3 - Select One

    The hostel canteen charges Rs 25 for lunch and Rs 8 for milk for each day. Then, how much money do you spend in 5 days on these things?

    ARs 120
    BRs 135
    CRs 165
    DRs 185