Doubtnut Promotions Sticky

In a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Let the number of days in which 150 workers finish the work be x.
150x=150+146+142+(x+8)
The above series is an AP with a=150,andd=4,n=x+8
150x=(x+82)[2(150)+(x+81)(4)]
150x=(x+8)(1502x14)
75x=(x+8)(68x)
x2+15x544=0
Solving above equation, we get
x = -32 or 17
But x cannot be negative.
So x = 17
Hence the number of days in which the work had to be completed by 150 workers is 17.
Required number of days=17+8=25

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.

    A24 days
    B40 days
    C17 days
    D25 days
  • Question 2 - Select One

    A contractor planned to finish work in 12 days and employed a certain number of men. However, 6 of them remained absent from the very first day. The rest could finish the work in 20 days. The number of men originally employed were:
    एक ठेकेदार ने किसी कार्य को 12 दिनों में समाप्त करने की योजना बनाई और निश्चित संख्या में पुरुषों को काम पर लगाया | हालाँकि, इनमें से 6 पहले ही दिन से अनुपस्थिति रहे | शेष पुरुष इस कार्य को 20 दिनों में समाप्त कर सके |आरंभ में कितने पुरुषों को कार्य पर लगाया गया था ?

    A24
    B20
    C18
    D15
  • Question 3 - Select One

    15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:

    A10
    B20
    C30
    D35