56 workers canfinish a piece of work in 14 days. If the work
is to be completed in 8 days, then how many extra workers
are required ?
A
36
B
48
C
44
D
42
Text Solution
The correct Answer is:(d)
Here, M1=56,D1=14,M2=?,D2=8
M1D1=M2D2
56×14=M2×8
⇒M2=98
Hence, extra workers to be required
=98−56=42
|
Topper's Solved these Questions
Similar Questions
Knowledge Check
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B8C14D1642 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B6C14D16In a field 6 workers complete a task in 16 days.If this task is to be completed in 4 days,then how many workers will be required?
A20B14C24D28
If 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionA can do a piece of work in 14 days while B can do it in 28 days. In how many days, working together will they complete the whole work?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View SolutionA can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?
View Solution