A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
To solve the problem step by step, let's break down the information and calculations as follows:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 45 days, so A's work in one day is 145.
- B can complete the work in 40 days, so B's work in one day is 140.
Hint: To find the work done in one day, take the reciprocal of the number of days each person takes to complete the work.
Step 2: Calculate the combined work done by A and B in one day.
- The combined work done by A and B in one day is:
Work by A and B in one day=145+140
- To add these fractions, find a common denominator. The least common multiple of 45 and 40 is 360.
- Convert each fraction:
145=8360,140=9360
- Therefore,
145+140=8360+9360=17360
Hint: When adding fractions, always find a common denominator to combine them.
Step 3: Determine the amount of work B completed in 23 days.
- B works at a rate of 140 per day. Thus, in 23 days, B completes:
Work done by B=23×140=2340
Hint: To find the total work done over multiple days, multiply the daily work rate by the number of days worked.
Step 4: Calculate the remaining work after B's contribution.
- The total work is considered as 1 (whole work). The remaining work after B's contribution is:
Remaining work=1−2340=4040−2340=1740
Hint: To find the remaining work, subtract the work done from the total work.
Step 5: Determine how much work A and B did together before A left.
- Let x be the number of days A and B worked together. The work done by A and B together in x days is:
Work done by A and B in x days=x×17360
- We know that the work done by A and B together is equal to the remaining work:
x×17360=1740
Hint: Set up an equation to relate the work done together to the remaining work.
Step 6: Solve for x.
- To find x, rearrange the equation:
x=174017360=1740×36017
- The 17 cancels out:
x=36040=9
Hint: When dividing fractions, multiply by the reciprocal of the divisor.
Conclusion
- A left after 9 days of working together with B.
Final Answer: A left after 9 days.
- A can complete the work in 45 days, so A's work in one day is 145.
- B can complete the work in 40 days, so B's work in one day is 140.
- The combined work done by A and B in one day is:
Work by A and B in one day=145+140
- To add these fractions, find a common denominator. The least common multiple of 45 and 40 is 360.
- Convert each fraction:
145=8360,140=9360
- Therefore,
145+140=8360+9360=17360
- B works at a rate of 140 per day. Thus, in 23 days, B completes:
Work done by B=23×140=2340
- The total work is considered as 1 (whole work). The remaining work after B's contribution is:
Remaining work=1−2340=4040−2340=1740
- Let x be the number of days A and B worked together. The work done by A and B together in x days is:
Work done by A and B in x days=x×17360
- We know that the work done by A and B together is equal to the remaining work:
x×17360=1740
- To find x, rearrange the equation:
x=174017360=1740×36017
- The 17 cancels out:
x=36040=9
- A left after 9 days of working together with B.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 759days b. 8 days c. 9 days d. 1425days
View Solution
Knowledge Check
- Question 1 - Select One
A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 days - Question 2 - Select One
A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
A1425 daysB9daysC8daysD759 days - Question 3 - Select One
A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
A2 daysB3 daysC1 dayDNone of these
A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some das and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
View Solution