A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work rates of A and B
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
Step 2: Calculate the combined work rate of A and B
- The combined work rate of A and B together is:
Combined work rate=110+115
- To add these fractions, we need a common denominator. The least common multiple of 10 and 15 is 30.
110=330,115=230
- Therefore,
Combined work rate=330+230=530=16
- This means A and B together can complete 16 of the work in one day.
Step 3: Determine the amount of work A completed in 5 days
- A finished the remaining work in 5 days. Since A's work rate is 110, the amount of work A completed in 5 days is:
Work done by A in 5 days=5×110=510=12
- This means A completed half of the work in the last 5 days.
Step 4: Determine the work done by A and B together before B left
- Since A completed half of the work alone, it implies that A and B together completed the other half of the work before B left.
- Let x be the number of days A and B worked together. The work done by A and B together in x days is:
Work done by A and B in x days=x×16
- We know that this work equals half of the total work:
x×16=12
Step 5: Solve for x
- To find x, we can rearrange the equation:
x=1/21/6=12×61=3
- Thus, A and B worked together for 3 days before B left.
Conclusion
B left after 3 days from the start.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- The combined work rate of A and B together is:
Combined work rate=110+115
- To add these fractions, we need a common denominator. The least common multiple of 10 and 15 is 30.
110=330,115=230
- Therefore,
Combined work rate=330+230=530=16
- This means A and B together can complete 16 of the work in one day.
- A finished the remaining work in 5 days. Since A's work rate is 110, the amount of work A completed in 5 days is:
Work done by A in 5 days=5×110=510=12
- This means A completed half of the work in the last 5 days.
- Since A completed half of the work alone, it implies that A and B together completed the other half of the work before B left.
- Let x be the number of days A and B worked together. The work done by A and B together in x days is:
Work done by A and B in x days=x×16
- We know that this work equals half of the total work:
x×16=12
- To find x, we can rearrange the equation:
x=1/21/6=12×61=3
- Thus, A and B worked together for 3 days before B left.
B left after 3 days from the start.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - TEST YOUR CONCEPTS (Very Short Answer Type Questions)30videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Short Answer Type Questions15videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View Solution
Knowledge Check
- Question 1 - Select One
A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?
A3B5C7D9 - Question 2 - Select One
A and B can do a piece of work in 30 and 36 days respectively. They began the work together but A leaves after some days and B finished the remaining wrok in 25 days. After how many days did A leave?
A5 daysB10 daysC11 daysD6 days - Question 3 - Select One
Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?
A5 daysB4 daysC6 daysD3 days
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?
View SolutionA and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
View Solution