Doubtnut Promotions Sticky

A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and C can do the same in 12 days. Time taken by A, B and C together to do the job is

A

4 days

B

9 days

C

8 days

D

5 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine the time taken by A, B, and C together to complete the work based on the information given about their individual and pair work rates.

1. Understanding the Work Rates:
- Let the total work be represented in units. We can assume the total work is 1 unit for simplicity.
- A and B can complete the work in 15 days, so their combined work rate is:
Work rate of A and B=115 units/day

- B and C can complete the work in 10 days, so their combined work rate is:
Work rate of B and C=110 units/day

- A and C can complete the work in 12 days, so their combined work rate is:
Work rate of A and C=112 units/day

2. Setting Up the Equations:
- Let the work rates of A, B, and C be a, b, and c respectively. We can set up the following equations based on the combined work rates:
a+b=115(1)
b+c=110(2)
a+c=112(3)

3. Adding the Equations:
- Adding equations (1), (2), and (3) gives:
(a+b)+(b+c)+(a+c)=115+110+112
- This simplifies to:
2a+2b+2c=115+110+112
- Dividing everything by 2:
a+b+c=12(115+110+112)(4)

4. Finding a Common Denominator:
- The least common multiple (LCM) of 15, 10, and 12 is 60. We can convert the fractions:
115=460,110=660,112=560
- Thus:
115+110+112=4+6+560=1560=14

5. Substituting Back:
- Substituting back into equation (4):
a+b+c=1214=18

6. Calculating Time Taken by A, B, and C Together:
- The combined work rate of A, B, and C is 18 units/day. Therefore, the time taken by A, B, and C together to complete the work is:
Time=Total WorkCombined Work Rate=118=8 days

Final Answer:
The time taken by A, B, and C together to do the job is 8 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B can do a work in 12 days, Band C can do the same work in 15 days, C and A can do the same work in 20 days. The time taken by A, B and C to do the same work is

    A5 days
    B10 days
    C15 days
    D20 days
  • Question 2 - Select One

    A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

    A28 days
    B14 days
    C5 57 days
    D8 27 days
  • Question 3 - Select One

    If A, B and C can do a piece of work in 5 days, B, C and D can do the same work in 10 days, C, D, and A can do the same work in 15 days, D, A and B can do the same work in 30 days. Find the time taken by A+B+C+D ?

    AA)9 days
    BB)7 days
    CC)9.5 days
    DD)7.5 days