A group of workers having equal efficiency can complete a job in 4 days. But it so happened that every alternate day starting from the second day, 3 workers are withdrawn from the job and every alternate day starting from the third day, 2 workers are added to the group. If it now takes 7 days to complete the job, find the number of workers who started the job. 4 b. 5 c. 6 d. 8
To solve the problem step by step, let's break it down clearly:
Step 1: Understand the Problem
We know that a group of workers can complete a job in 4 days. We need to find out how many workers started the job if due to certain changes, it now takes them 7 days to complete the job.
Step 2: Define Variables
Let n be the number of workers who started the job.
Step 3: Determine Work Done by Workers
If n workers can complete the job in 4 days, then the total work can be expressed as:
Total Work=n×4 (workers × days)
This means that the work done by one worker in one day is:
Work done by one worker in one day=14n
Step 4: Calculate Work Done Each Day
Now, let's calculate how much work is done each day considering the changes in the number of workers:
- Day 1: All n workers are present.
Work done=n×14n=14
- Day 2: 3 workers are withdrawn, so n−3 workers are present.
Work done=(n−3)×14n=n−34n
- Day 3: 2 workers are added, so n−1 workers are present.
Work done=(n−1)×14n=n−14n
- Day 4: 3 workers are withdrawn again, so n−4 workers are present.
Work done=(n−4)×14n=n−44n
- Day 5: 2 workers are added, so n−2 workers are present.
Work done=(n−2)×14n=n−24n
- Day 6: 3 workers are withdrawn, so n−5 workers are present.
Work done=(n−5)×14n=n−54n
- Day 7: 2 workers are added, so n−3 workers are present.
Work done=(n−3)×14n=n−34n
Step 5: Total Work Done in 7 Days
Now, we can sum the work done over the 7 days:
Total Work=14+n−34n+n−14n+n−44n+n−24n+n−54n+n−34n
Combining these fractions:
Total Work=14+(n−3)+(n−1)+(n−4)+(n−2)+(n−5)+(n−3)4n
=14+6n−184n=14+6(n−3)4n
Step 6: Set Up the Equation
Since the total work done in 7 days is equal to 1 (the whole job), we set up the equation:
14+6(n−3)4n=1
Step 7: Solve the Equation
Multiply through by 4n to eliminate the fractions:
n+6(n−3)=4n
n+6n−18=4n
7n−18=4n
7n−4n=18
3n=18
n=6
Conclusion
The number of workers who started the job is n=6.
We know that a group of workers can complete a job in 4 days. We need to find out how many workers started the job if due to certain changes, it now takes them 7 days to complete the job.
Let n be the number of workers who started the job.
If n workers can complete the job in 4 days, then the total work can be expressed as:
Total Work=n×4 (workers × days)
This means that the work done by one worker in one day is:
Work done by one worker in one day=14n
Now, let's calculate how much work is done each day considering the changes in the number of workers:
Work done=n×14n=14
Work done=(n−3)×14n=n−34n
Work done=(n−1)×14n=n−14n
Work done=(n−4)×14n=n−44n
Work done=(n−2)×14n=n−24n
Work done=(n−5)×14n=n−54n
Work done=(n−3)×14n=n−34n
Now, we can sum the work done over the 7 days:
Total Work=14+n−34n+n−14n+n−44n+n−24n+n−54n+n−34n
Combining these fractions:
Total Work=14+(n−3)+(n−1)+(n−4)+(n−2)+(n−5)+(n−3)4n
=14+6n−184n=14+6(n−3)4n
Since the total work done in 7 days is equal to 1 (the whole job), we set up the equation:
14+6(n−3)4n=1
Multiply through by 4n to eliminate the fractions:
n+6(n−3)=4n
n+6n−18=4n
7n−18=4n
7n−4n=18
3n=18
n=6
The number of workers who started the job is n=6.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
A7B6C14D16 - Question 2 - Select One
12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?
A2 hrsB3.2 hrsC3 .5 hrsD3 hrs - Question 3 - Select One
24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :
A30B40C25D50
56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:
View Solution24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution22 men can complete a job in 16days. In how many days, will 32 men complete that job?
View SolutionA man completes 49 of a job in 12 days. At this rate, how many more days will it take him to finish the job ?
View Solution