If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work? 8 days b. 12 days c. 14 days d. cannot be determined e. none of these
To solve the problem, we will first determine the work done by one man and one boy in a day, then find out how much work 5 men and 6 boys can do together in a day, and finally calculate how many days they will take to complete the work.
1. Determine the work done by 3 men in 21 days:
- If 3 men can finish the work in 21 days, then the total work can be represented as:
Total Work=3 men×21 days=63 man-days
2. Calculate the work done by 1 man in 1 day:
- The work done by 1 man in 1 day is:
Work done by 1 man in 1 day=163 of the work
3. Determine the work done by 9 boys in 21 days:
- Similarly, if 9 boys can finish the same work in 21 days, then:
Total Work=9 boys×21 days=189 boy-days
4. Calculate the work done by 1 boy in 1 day:
- The work done by 1 boy in 1 day is:
Work done by 1 boy in 1 day=1189 of the work
5. Calculate the combined work done by 5 men and 6 boys in 1 day:
- Work done by 5 men in 1 day:
Work done by 5 men=5×163=563
- Work done by 6 boys in 1 day:
Work done by 6 boys=6×1189=6189
- To add these fractions, we need a common denominator. The least common multiple of 63 and 189 is 189.
- Convert 563 to have a denominator of 189:
563=5×363×3=15189
- Now add the two fractions:
Total work done in 1 day=15189+6189=21189=19
6. Calculate the number of days to complete the work:
- If 5 men and 6 boys together do 19 of the work in one day, then the total number of days to complete the work is:
Days to complete the work=119=9 days
Final Answer:
The number of days required for 5 men and 6 boys to complete the work is 9 days.
- If 3 men can finish the work in 21 days, then the total work can be represented as:
Total Work=3 men×21 days=63 man-days
- The work done by 1 man in 1 day is:
Work done by 1 man in 1 day=163 of the work
- Similarly, if 9 boys can finish the same work in 21 days, then:
Total Work=9 boys×21 days=189 boy-days
- The work done by 1 boy in 1 day is:
Work done by 1 boy in 1 day=1189 of the work
- Work done by 5 men in 1 day:
Work done by 5 men=5×163=563
- Work done by 6 boys in 1 day:
Work done by 6 boys=6×1189=6189
- To add these fractions, we need a common denominator. The least common multiple of 63 and 189 is 189.
- Convert 563 to have a denominator of 189:
563=5×363×3=15189
- Now add the two fractions:
Total work done in 1 day=15189+6189=21189=19
- If 5 men and 6 boys together do 19 of the work in one day, then the total number of days to complete the work is:
Days to complete the work=119=9 days
The number of days required for 5 men and 6 boys to complete the work is 9 days.
Topper's Solved these Questions
Similar Questions
Knowledge Check
- Question 1 - Select One
If 3 men or 9 boys can finish a work in 21 days . In how many days, can 5 men and 6 boys together do the same work ?
A12 daysB8 daysC14 daysDNone the above - Question 2 - Select One
If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days - Question 3 - Select One
If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?
A4 daysB5 daysC3 daysD2 days
12 men or 24 boys can do a work in 20 days. In how many days, will 24 men and 12 boys together complete the same work ?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View SolutionIf 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?
View SolutionIf x men can do a piece of work in y days, in how many days will x men do the same work ?
View SolutionIf 4 men or 8 women can piece of work 15 days how many can 6 men and 12 women do the same piece of work ?
View Solution