Certain men can do a piece of work in 22 days. If the number of men decreses by 55, then they will take 11 days more to comlete the same work. Find the number of men present intially.
165
155
185
175
The correct Answer is:A
To solve the problem, we will follow these steps:
Step 1: Define Variables
Let the number of men initially be X.
Step 2: Calculate Work Done by Initial Men
If X men can complete the work in 22 days, the total work can be expressed in terms of man-days:
Total Work=X×22
Step 3: Calculate Work Done by Reduced Number of Men
When the number of men decreases by 55, the number of men becomes X−55. According to the problem, these men take 11 days more, which means they complete the work in:
22+11=33 days
The total work done by these men can also be expressed as:
Total Work=(X−55)×33
Step 4: Set Up the Equation
Since both expressions represent the same total work, we can set them equal to each other:
X×22=(X−55)×33
Step 5: Expand and Rearrange the Equation
Expanding the right side:
22X=33X−55×33
22X=33X−1815
Now, rearranging the equation to isolate X:
22X−33X=−1815
−11X=−1815
Dividing both sides by -11:
X=181511
X=165
Step 6: Conclusion
Thus, the number of men present initially is 165.
Let the number of men initially be X.
If X men can complete the work in 22 days, the total work can be expressed in terms of man-days:
Total Work=X×22
When the number of men decreases by 55, the number of men becomes X−55. According to the problem, these men take 11 days more, which means they complete the work in:
22+11=33 days
The total work done by these men can also be expressed as:
Total Work=(X−55)×33
Since both expressions represent the same total work, we can set them equal to each other:
X×22=(X−55)×33
Expanding the right side:
22X=33X−55×33
22X=33X−1815
Now, rearranging the equation to isolate X:
22X−33X=−1815
−11X=−1815
Dividing both sides by -11:
X=181511
X=165
Thus, the number of men present initially is 165.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
Knowledge Check
- Question 1 - Select One
If 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
A15B30C20D35 - Question 2 - Select One
If x men can do a piece of work In x days, then the number of days in which y men can do the same work is
Axy daysBy2x daysCx2y daysDx2y days - Question 3 - Select One
If 35 men can finish a piece of work in 8 days, then the number of men who can do the same work in 10 days is :
A38B28C19D17
If 6 men can do a piece of work in 8 days, then find the number of days in which 8 men can do the same work.
View SolutionIf six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days
View Solution34 men can do a piece of work in 12 days . How many days will 51 men take to do it
View Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View Solution450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?
View Solution