Doubtnut Promotions Sticky

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A

38

B

51

C

46

D

62

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


Find the work done by A in 14 days and then find the remianing work and proceed.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Sunny can complete a piece of work in 30 days He worked for 6 days and left. Bunny completed the remaining work in 16 days. In how many days can the entire work kbe completed if they worik together?

    A8
    B12
    C16
    D20
  • Question 2 - Select One

    A and B together can complete a work in 12 days. A alone works for 8 days and B alone can complete the remaining work in 20 days. Then in how many days B alone can complete the whole work?

    A60 days
    B36 days
    C45 days
    D24 days
  • Question 3 - Select One

    A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?

    A12
    B68
    C72
    D90