Doubtnut Promotions Sticky

Ram , Shaym and Tarun are three people on a job. Each takes m times the time taken by other two, to comleted a job. Find m

A

1

B

2

C

12

D

None of these

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:B


(i) Frame equation and solve
(ii) Let the capacities or work complete in oe day by the three people be 1R,1Sand1T.
Take1R=1m(1S+1T),
1S=1m(1T+1R)and1T=1m(1R+1S)
Add the above three equations and find m.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A man take 80 days to complete a job. To complete this job, 4 men, 8 women and 4 machines take 5 days. Alternatively, 4 men, 1, women and 2 machines take 10 days to complete the job. Find the time taken by a women to complete the job (in says)

    A90
    B100
    C105
    D120
  • Question 2 - Select One

    The efficiency of A, B and C is the same. They started working on a certain job. After 5 days a leaves, after 5 moere days B leaves and C completes the remaining work in 5 more days. Find the time taken by eahc of them alone to complete the job. (in days)?

    A20
    B30
    C40
    D45
  • Question 3 - Select One

    Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :

    A8 days
    B3835 days
    C152
    D1313