Ram , Shaym and Tarun are three people on a job. Each takes m times the time taken by other two, to comleted a job. Find m
1
2
12
None of these
The correct Answer is:B
(i) Frame equation and solve
(ii) Let the capacities or work complete in oe day by the three people be 1R,1Sand1T.
Take1R=1m(1S+1T),
1S=1m(1T+1R)and1T=1m(1R+1S)
Add the above three equations and find m.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 219videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 321videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS50videos
TIME AND WORK
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 36videos
BANKING AND COMPUTING
Similar Questions
……… determines the standard time taken to perform a well-defined job.
View Solution4 women and 3 men can do a piece of work in 2 days while 6 women and 2 men can also finish it in 2 days. Now find the time taken by one woman to complete the same job working alone. Also, find the time one man takes to complete the same job working alone.
View Solution
Knowledge Check
- Question 1 - Select One
A man take 80 days to complete a job. To complete this job, 4 men, 8 women and 4 machines take 5 days. Alternatively, 4 men, 1, women and 2 machines take 10 days to complete the job. Find the time taken by a women to complete the job (in says)
A90B100C105D120 - Question 2 - Select One
The efficiency of A, B and C is the same. They started working on a certain job. After 5 days a leaves, after 5 moere days B leaves and C completes the remaining work in 5 more days. Find the time taken by eahc of them alone to complete the job. (in days)?
A20B30C40D45 - Question 3 - Select One
Bunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
A8 daysB3835 daysC152D1313
The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
View Solution4 women and 3 men can do a piece of work in 2 days while 6 women and 2 men can also finish it in 2 days. Now find the time taken by one woman to complete the same job working alone. Also, find the time one man takes to complete the same job working alone.
View SolutionBunty and Babli working together completed a job in 8 days. If Bunty worked twice efficiently as he actually did and Babli worked as efficiently as she actually did, the work would have been completed in 6 days. Find the time taken by Bunty to complete the job alone :
View SolutionThe time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days.
View SolutionThe sum of the times taken by train P and train Q to cross their own lengths is twice the time taken by them to cross each other when they are travelling in opposite direction to each other . If P takes 20 s to cross a stationary pole, then find the time taken by Q to do the same .(in seconds)
View Solution