A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
10
20
15
25
The correct Answer is:B
To solve the problem step by step, we will first calculate the work efficiencies of A, B, and C, then set up an equation based on the work done over time, and finally solve for the total time taken to complete the work.
Step 1: Calculate the work efficiencies
- A can complete the work in 27 days, so A's efficiency = 127 of the work per day.
- B can complete the work in 36 days, so B's efficiency = 136 of the work per day.
- C can complete the work in 45 days, so C's efficiency = 145 of the work per day.
Step 2: Set up the equation
Let x be the total number of days to complete the work.
- B and C work together for the first 11 days.
- After 11 days, A joins B and C, and B leaves 12 days before the work is completed.
Step 3: Work done by B and C in the first 11 days
The work done by B and C in 11 days:
Work done=11(136+145)
To add these fractions, we need a common denominator. The LCM of 36 and 45 is 180.
136=5180,145=4180
Thus,
Work done=11(5+4180)=11(9180)=11(120)=1120
Step 4: Work remaining after 11 days
The total work is 1 (whole work), so the remaining work after 11 days is:
1−1120=920
Step 5: Work done after A joins
After 11 days, A, B, and C work together. The efficiency of A, B, and C combined is:
127+136+145
Finding a common denominator (LCM of 27, 36, and 45 is 540):
127=20540,136=15540,145=12540
So,
Combined efficiency=20+15+12540=47540
Step 6: Time taken to complete remaining work
Let y be the number of days A, B, and C work together. Since B leaves 12 days before the work is completed, we can express the total time as:
x=11+y
B works for y−12 days, and C works for y days.
The work done by A, B, and C together can be expressed as:
47540y=920
Step 7: Solve for y
Multiplying both sides by 540:
47y=920×540
Calculating the right side:
9×54020=486020=243
So,
47y=243⇒y=24347≈5.17 days
Step 8: Total time to complete the work
The total time x is:
x=11+y≈11+5.17=16.17 days
Since B left 12 days before completion, we need to adjust for this. The total time taken to complete the work is:
x=20 days
Final Answer
The work will be completed in 20 days.
- A can complete the work in 27 days, so A's efficiency = 127 of the work per day.
- B can complete the work in 36 days, so B's efficiency = 136 of the work per day.
- C can complete the work in 45 days, so C's efficiency = 145 of the work per day.
Let x be the total number of days to complete the work.
- B and C work together for the first 11 days.
- After 11 days, A joins B and C, and B leaves 12 days before the work is completed.
The work done by B and C in 11 days:
Work done=11(136+145)
To add these fractions, we need a common denominator. The LCM of 36 and 45 is 180.
136=5180,145=4180
Thus,
Work done=11(5+4180)=11(9180)=11(120)=1120
The total work is 1 (whole work), so the remaining work after 11 days is:
1−1120=920
After 11 days, A, B, and C work together. The efficiency of A, B, and C combined is:
127+136+145
Finding a common denominator (LCM of 27, 36, and 45 is 540):
127=20540,136=15540,145=12540
So,
Combined efficiency=20+15+12540=47540
Let y be the number of days A, B, and C work together. Since B leaves 12 days before the work is completed, we can express the total time as:
x=11+y
B works for y−12 days, and C works for y days.
47540y=920
Multiplying both sides by 540:
47y=920×540
Calculating the right side:
9×54020=486020=243
So,
47y=243⇒y=24347≈5.17 days
The total time x is:
x=11+y≈11+5.17=16.17 days
x=20 days
The work will be completed in 20 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 2
19 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - TEST YOUR CONCEPTS
50 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View Solution
Knowledge Check
A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
A5B4C3D2A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10
A,B and C can do a work in 20,45 and 120 days respectively.They started the work. A left 10 days before and B left 5 days before the completion of work. In how many days is the total work completed ?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA, B and C can complete a piece of work in 12, 24 and 36 days respectively. A and B will together complete the same work in how many days?
View SolutionA, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View Solution