A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?

A

10

B

20

C

15

D

25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first calculate the work efficiencies of A, B, and C, then set up an equation based on the work done over time, and finally solve for the total time taken to complete the work.

Step 1: Calculate the work efficiencies
- A can complete the work in 27 days, so A's efficiency = 127 of the work per day.
- B can complete the work in 36 days, so B's efficiency = 136 of the work per day.
- C can complete the work in 45 days, so C's efficiency = 145 of the work per day.

Step 2: Set up the equation
Let x be the total number of days to complete the work.
- B and C work together for the first 11 days.
- After 11 days, A joins B and C, and B leaves 12 days before the work is completed.

Step 3: Work done by B and C in the first 11 days
The work done by B and C in 11 days:
Work done=11(136+145)
To add these fractions, we need a common denominator. The LCM of 36 and 45 is 180.
136=5180,145=4180
Thus,
Work done=11(5+4180)=11(9180)=11(120)=1120

Step 4: Work remaining after 11 days
The total work is 1 (whole work), so the remaining work after 11 days is:
11120=920

Step 5: Work done after A joins
After 11 days, A, B, and C work together. The efficiency of A, B, and C combined is:
127+136+145
Finding a common denominator (LCM of 27, 36, and 45 is 540):
127=20540,136=15540,145=12540
So,
Combined efficiency=20+15+12540=47540

Step 6: Time taken to complete remaining work
Let y be the number of days A, B, and C work together. Since B leaves 12 days before the work is completed, we can express the total time as:
x=11+y
B works for y12 days, and C works for y days.

The work done by A, B, and C together can be expressed as:
47540y=920

Step 7: Solve for y
Multiplying both sides by 540:
47y=920×540
Calculating the right side:
9×54020=486020=243
So,
47y=243y=243475.17 days

Step 8: Total time to complete the work
The total time x is:
x=11+y11+5.17=16.17 days

Since B left 12 days before completion, we need to adjust for this. The total time taken to complete the work is:
x=20 days

Final Answer
The work will be completed in 20 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2
  • A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

    A5
    B4
    C3
    D2
  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10