Doubtnut Promotions Sticky

If X works 3 times as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they can complete the work working together.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

If Y does the work in 3 days, X does it in 1 day, i.e., the difference is 2 days. But the actual difference is 40 days.
If difference is 2 days, X takes 1 day and Y takes 3 days. If difference is 40 days(i.e., 20 times),
X takes 20 days and Y takes 60 days.
Time taken together =20×6020+60=15 days.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A is thrice as efficient as B and hence completes a work in 40
    days less than the number days taken by B. What will be
    the number of days taken by both of them when working
    together ?

    A22.5 days
    B15 days
    C20 days
    D18 days
  • Question 2 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days
  • Question 3 - Select One

    If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

    A25 days
    B45 days
    C50 days
    D20 days