Doubtnut Promotions Sticky

P,Q and R started a piece of work. They worked on it for 5 days, which P left

Text Solution
Verified by Experts

(a) (p+q+r) worked for 5 days, (Q+R) worked for 5 days and R worked for 5 days to complete the work.
(b) P worked for 5 days, Q worked for 10 days and R worked for 15 days to complete the work.(iii) Find the part of the work done by Q and R.
(c ) Then find the part of the work done by P.
(d) Compare them.
When certain people work for the same number of days each, then the ratio of the total work done will be the same as the work done by each of them per day. Hence, if all the people involved work for the same number of days, then the earning can directly be distributed in the ratio of work done per day by each of them . The following example is useful to understand this statement.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?

    A30 days
    B20 days
    C60 days
    D50 days
  • Question 2 - Select One

    P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

    A12
    B18
    C4
    D27
  • Question 3 - Select One

    P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

    A12
    B18
    C4
    D27