P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?
10
11
10711
10911
The correct Answer is:B
To solve the problem step by step, we will first find the work done by each person per day, then determine how long they worked together and when they left, and finally calculate the total time taken to complete the work.
1. Calculate the work done by P, Q, and R in one day:
- P can complete the work in 18 days, so P's work per day = 118.
- Q can complete the work in 36 days, so Q's work per day = 136.
- R can complete the work in 54 days, so R's work per day = 154.
2. Calculate the total work done by P, Q, and R in one day when they work together:
Total work per day=118+136+154
To add these fractions, we need a common denominator. The least common multiple (LCM) of 18, 36, and 54 is 108.
118=6108,136=3108,154=2108
Therefore,
Total work per day=6+3+2108=11108
3. Let the total number of days taken to complete the work be X days.
- P works for X days.
- Q works for X−1 days (since Q leaves 1 day before completion).
- R works for X−5 days (since R leaves 5 days before completion).
4. Set up the equation for the total work done:
Total work=Work done by P+Work done by Q+Work done by R
1=(X18)+(X−136)+(X−554)
5. Multiply through by 108 to eliminate the denominators:
108=6X+3(X−1)+2(X−5)
Expanding this gives:
108=6X+3X−3+2X−10
Combining like terms:
108=11X−13
6. Solve for X:
11X=108+13
11X=121
X=12111=11
7. Conclusion:
The total number of days taken to complete the work is 11 days.
- P can complete the work in 18 days, so P's work per day = 118.
- Q can complete the work in 36 days, so Q's work per day = 136.
- R can complete the work in 54 days, so R's work per day = 154.
Total work per day=118+136+154
To add these fractions, we need a common denominator. The least common multiple (LCM) of 18, 36, and 54 is 108.
118=6108,136=3108,154=2108
Therefore,
Total work per day=6+3+2108=11108
- P works for X days.
- Q works for X−1 days (since Q leaves 1 day before completion).
- R works for X−5 days (since R leaves 5 days before completion).
Total work=Work done by P+Work done by Q+Work done by R
1=(X18)+(X−136)+(X−554)
108=6X+3(X−1)+2(X−5)
Expanding this gives:
108=6X+3X−3+2X−10
Combining like terms:
108=11X−13
11X=108+13
11X=121
X=12111=11
The total number of days taken to complete the work is 11 days.
Topper's Solved these Questions
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
- TIME AND WORK PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)
33 Videos
- TIME AND DISTANCE BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )
3 Videos
- TIME AND WORK, PIPES AND CISTERNSBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)
7 Videos
Similar Questions
A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View SolutionA and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?
View Solution
Knowledge Check
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
A14B12C18D10A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
View SolutionA, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?
View SolutionA , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?
View SolutionA and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?
View SolutionP alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed
View Solution