P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

A

10

B

11

C

10711

D

10911

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will first find the work done by each person per day, then determine how long they worked together and when they left, and finally calculate the total time taken to complete the work.

1. Calculate the work done by P, Q, and R in one day:
- P can complete the work in 18 days, so P's work per day = 118.
- Q can complete the work in 36 days, so Q's work per day = 136.
- R can complete the work in 54 days, so R's work per day = 154.

2. Calculate the total work done by P, Q, and R in one day when they work together:
Total work per day=118+136+154
To add these fractions, we need a common denominator. The least common multiple (LCM) of 18, 36, and 54 is 108.
118=6108,136=3108,154=2108
Therefore,
Total work per day=6+3+2108=11108

3. Let the total number of days taken to complete the work be X days.
- P works for X days.
- Q works for X1 days (since Q leaves 1 day before completion).
- R works for X5 days (since R leaves 5 days before completion).

4. Set up the equation for the total work done:
Total work=Work done by P+Work done by Q+Work done by R
1=(X18)+(X136)+(X554)

5. Multiply through by 108 to eliminate the denominators:
108=6X+3(X1)+2(X5)
Expanding this gives:
108=6X+3X3+2X10
Combining like terms:
108=11X13

6. Solve for X:
11X=108+13
11X=121
X=12111=11

7. Conclusion:
The total number of days taken to complete the work is 11 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?

    A14
    B12
    C18
    D10
  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these