Doubtnut Promotions Sticky

A and B working together can complete a piece of work in 6 days, B and C in 10 days, C and A in 712 days. The number of days required by A,B and C respectively to complete the work individually is

A

15,20,30

B

10,20,30

C

10,15,30

D

20,15,10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will determine the individual efficiencies of A, B, and C based on the information given about their combined work rates.

Step 1: Understand the combined work rates
- A and B can complete the work in 6 days.
- B and C can complete the work in 10 days.
- C and A can complete the work in 7.5 days (which is 7 and 1/2 days).

Step 2: Calculate the work done per day by each pair
1. A and B together:
Work done in 1 day=16 of the work=5 units (assuming total work is 30 units)

2. B and C together:
Work done in 1 day=110 of the work=3 units

3. C and A together:
Work done in 1 day=17.5 of the work=3015=4 units

Step 3: Set up equations based on the work done
Let:
- A's efficiency = a
- B's efficiency = b
- C's efficiency = c

From the work done per day:
1. a+b=5 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)

Step 4: Solve the equations
Add all three equations:
(a+b)+(b+c)+(c+a)=5+3+4
This simplifies to:
2a+2b+2c=12
Dividing through by 2 gives:
a+b+c=6(Equation 4)

Step 5: Substitute to find individual efficiencies
1. From Equation 1: b=5a
2. Substitute b in Equation 2:
(5a)+c=3c=3(5a)=a2
3. Substitute c in Equation 3:
(a2)+a=42a2=42a=6a=3
4. Now substitute a back to find b and c:
- From Equation 1: b=53=2
- From c=a2: c=32=1

Step 6: Determine the number of days each person takes to complete the work individually
- Total work = 30 units
1. Days taken by A:
Days=30a=303=10 days
2. Days taken by B:
Days=30b=302=15 days
3. Days taken by C:
Days=30c=301=30 days

Final Answer:
- A takes 10 days,
- B takes 15 days,
- C takes 30 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B working together can complete a piece of work in 6 days, B and C in 10 days, C and A in 712 days. The number of days required by A,B and C respectively to complete the work individually is

    A15, 20, 30
    B10, 20, 30
    C10, 15, 30
    D20, 15, 10
  • Question 2 - Select One

    A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?

    A80 days
    B100 days
    C120 days
    D150 days
  • Question 3 - Select One

    A and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is

    A10
    B12
    C9
    D15