A and B working together can complete a piece of work in 6 days, B and C in 10 days, C and A in 712 days. The number of days required by A,B and C respectively to complete the work individually is
15,20,30
10,20,30
10,15,30
20,15,10
The correct Answer is:C
To solve the problem step by step, we will determine the individual efficiencies of A, B, and C based on the information given about their combined work rates.
Step 1: Understand the combined work rates
- A and B can complete the work in 6 days.
- B and C can complete the work in 10 days.
- C and A can complete the work in 7.5 days (which is 7 and 1/2 days).
Step 2: Calculate the work done per day by each pair
1. A and B together:
Work done in 1 day=16 of the work=5 units (assuming total work is 30 units)
2. B and C together:
Work done in 1 day=110 of the work=3 units
3. C and A together:
Work done in 1 day=17.5 of the work=3015=4 units
Step 3: Set up equations based on the work done
Let:
- A's efficiency = a
- B's efficiency = b
- C's efficiency = c
From the work done per day:
1. a+b=5 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)
Step 4: Solve the equations
Add all three equations:
(a+b)+(b+c)+(c+a)=5+3+4
This simplifies to:
2a+2b+2c=12
Dividing through by 2 gives:
a+b+c=6(Equation 4)
Step 5: Substitute to find individual efficiencies
1. From Equation 1: b=5−a
2. Substitute b in Equation 2:
(5−a)+c=3⟹c=3−(5−a)=a−2
3. Substitute c in Equation 3:
(a−2)+a=4⟹2a−2=4⟹2a=6⟹a=3
4. Now substitute a back to find b and c:
- From Equation 1: b=5−3=2
- From c=a−2: c=3−2=1
Step 6: Determine the number of days each person takes to complete the work individually
- Total work = 30 units
1. Days taken by A:
Days=30a=303=10 days
2. Days taken by B:
Days=30b=302=15 days
3. Days taken by C:
Days=30c=301=30 days
Final Answer:
- A takes 10 days,
- B takes 15 days,
- C takes 30 days.
- A and B can complete the work in 6 days.
- B and C can complete the work in 10 days.
- C and A can complete the work in 7.5 days (which is 7 and 1/2 days).
1. A and B together:
Work done in 1 day=16 of the work=5 units (assuming total work is 30 units)
Work done in 1 day=110 of the work=3 units
Work done in 1 day=17.5 of the work=3015=4 units
Let:
- A's efficiency = a
- B's efficiency = b
- C's efficiency = c
1. a+b=5 (Equation 1)
2. b+c=3 (Equation 2)
3. c+a=4 (Equation 3)
Add all three equations:
(a+b)+(b+c)+(c+a)=5+3+4
This simplifies to:
2a+2b+2c=12
Dividing through by 2 gives:
a+b+c=6(Equation 4)
1. From Equation 1: b=5−a
2. Substitute b in Equation 2:
(5−a)+c=3⟹c=3−(5−a)=a−2
3. Substitute c in Equation 3:
(a−2)+a=4⟹2a−2=4⟹2a=6⟹a=3
4. Now substitute a back to find b and c:
- From Equation 1: b=5−3=2
- From c=a−2: c=3−2=1
- Total work = 30 units
1. Days taken by A:
Days=30a=303=10 days
2. Days taken by B:
Days=30b=302=15 days
3. Days taken by C:
Days=30c=301=30 days
- A takes 10 days,
- B takes 15 days,
- C takes 30 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK, PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
Similar Questions
Knowledge Check
- Question 1 - Select One
A and B working together can complete a piece of work in 6 days, B and C in 10 days, C and A in 712 days. The number of days required by A,B and C respectively to complete the work individually is
A15, 20, 30B10, 20, 30C10, 15, 30D20, 15, 10 - Question 2 - Select One
A and B together can complete a piece of work in 72 days, B and C together can complete it in 120 days, and A and C together in 90 days. In what time can A alone complete the work ?
A80 daysB100 daysC120 daysD150 days - Question 3 - Select One
A and B together can do a piece of work in 6 days . If A can alone do the work in 18 days then the number of days required for B to finsh the work is
A10B12C9D15
A and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :
View SolutionA can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
View SolutionA and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View Solution