A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?
203 days
253 days
6 days
5 days
The correct Answer is:C
To solve the problem step by step, let's break it down:
Step 1: Determine the work rates of A and B
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=112+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 12 and 15 is 60. Thus:
112=560and115=460
- Therefore, the combined work rate is:
Combined work rate=560+460=960=320
Step 3: Calculate the amount of work done in 4 days
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=320×4=1220=35
- To express this in terms of total work, if we consider the total work to be 60 units, then:
Work done in 4 days=60×35=36 units
Step 4: Calculate the remaining work
- The total work is 60 units, and after 4 days, 36 units have been completed. Therefore, the remaining work is:
Remaining work=60−36=24 units
Step 5: Determine how long it will take B to complete the remaining work
- B's work rate is 115 of the work per day. Therefore, in one day, B can complete:
Work done by B in 1 day=115 of the total work
- To find out how many days B needs to complete the remaining 24 units, we can set up the equation:
Days required by B=Remaining workWork done by B in 1 day=24115=24×15=6 days
Final Answer
B will take 6 more days to complete the remaining work.
---
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)
- When A and B work together, their combined work rate is:
Combined work rate=112+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 12 and 15 is 60. Thus:
112=560and115=460
- Therefore, the combined work rate is:
Combined work rate=560+460=960=320
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=320×4=1220=35
- To express this in terms of total work, if we consider the total work to be 60 units, then:
Work done in 4 days=60×35=36 units
- The total work is 60 units, and after 4 days, 36 units have been completed. Therefore, the remaining work is:
Remaining work=60−36=24 units
- B's work rate is 115 of the work per day. Therefore, in one day, B can complete:
Work done by B in 1 day=115 of the total work
- To find out how many days B needs to complete the remaining 24 units, we can set up the equation:
Days required by B=Remaining workWork done by B in 1 day=24115=24×15=6 days
B will take 6 more days to complete the remaining work.
Topper's Solved these Questions
- TIME AND WORKBook:KIRAN PUBLICATIONChapter:TIME AND WORKExercise:TYPE-III
Explore 31 Videos
- TIME AND WORKBook:KIRAN PUBLICATIONChapter:TIME AND WORKExercise:TYPE-IV
Explore 32 Videos
- TIME AND WORKBook:KIRAN PUBLICATIONChapter:TIME AND WORKExercise:TEST YOURSELF
Explore 25 Videos
- TIME AND DISTANCEBook:KIRAN PUBLICATIONChapter:TIME AND DISTANCEExercise:Type -XI
Explore 74 Videos
- TRIGONOMETRY Book:KIRAN PUBLICATIONChapter:TRIGONOMETRY Exercise:TEST YOURSELF
Explore 25 Videos
Similar Questions
A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?
View SolutionA and B can do a piece of work in 45 and 40 days repectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after
View Solution
Knowledge Check
A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
A6B8C5D10A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?
A2B52C114D95A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?
A1425 daysB9daysC8daysD759 days
A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave
View SolutionA and B can do a piece of work in 45 and 40 days respectively. They began the work together but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave?
View SolutionA and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:
View SolutionA and B can do a piece of work in 20 and 25 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave?
View Solution