A and B can do a piece of work in 12 days and 15 days respectively. They began to work together but A left after 4 days. In how many more days would B alone complete the remaining work ?

A

203 days

B

253 days

C

6 days

D

5 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's break it down:

Step 1: Determine the work rates of A and B
- A can complete the work in 12 days. Therefore, A's work rate is:
Work rate of A=112 (work per day)
- B can complete the work in 15 days. Therefore, B's work rate is:
Work rate of B=115 (work per day)

Step 2: Calculate the combined work rate of A and B
- When A and B work together, their combined work rate is:
Combined work rate=112+115
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 12 and 15 is 60. Thus:
112=560and115=460
- Therefore, the combined work rate is:
Combined work rate=560+460=960=320

Step 3: Calculate the amount of work done in 4 days
- In 4 days, the amount of work done by A and B together is:
Work done in 4 days=Combined work rate×4=320×4=1220=35
- To express this in terms of total work, if we consider the total work to be 60 units, then:
Work done in 4 days=60×35=36 units

Step 4: Calculate the remaining work
- The total work is 60 units, and after 4 days, 36 units have been completed. Therefore, the remaining work is:
Remaining work=6036=24 units

Step 5: Determine how long it will take B to complete the remaining work
- B's work rate is 115 of the work per day. Therefore, in one day, B can complete:
Work done by B in 1 day=115 of the total work
- To find out how many days B needs to complete the remaining 24 units, we can set up the equation:
Days required by B=Remaining workWork done by B in 1 day=24115=24×15=6 days

Final Answer
B will take 6 more days to complete the remaining work.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

    A6
    B8
    C5
    D10
  • A, B and C, one can do a piece of work in 9, 12 and 18 days respectively. They all started the work together, but A left after 3 days. In how many days, was the remaining work completed?

    A2
    B52
    C114
    D95
  • A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave ?

    A1425 days
    B9days
    C8days
    D759 days