Doubtnut Promotions Sticky

Thirty men can do a piece of work in 16 days working 8 hours a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 working a day?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
M2=30×16×8×2xx×12×10
30×16×8x=M2×12×102x
M1D1H1W1=M2D2H2W2
M2=64

A

CBAD

B

ACBD

C

ABCD

D

BACD

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step-by-step, we can follow the logical sequence of calculations based on the information given. Here’s how we can derive the solution:

Step 1: Understand the Given Information
We know that:
- 30 men can complete a piece of work in 16 days working 8 hours a day.
- We need to find out how many men (M2) are needed to complete another work, which is twice the first one (W2 = 2 * W1), in 10 days working 12 hours a day.

Step 2: Calculate the Total Work Done in the First Scenario
The total work (W1) can be calculated as:
W1=Number of men×Number of days×Number of hours per day
W1=30 men×16 days×8 hours/day
W1=3840 man-hours

Step 3: Calculate the Total Work for the Second Scenario
Since the second work is twice the first work:
W2=2×W1=2×3840=7680 man-hours

Step 4: Set Up the Equation Using the Work Formula
Using the formula for work:
M1×D1×H1W1=M2×D2×H2W2
Substituting the known values:
30×16×83840=M2×10×127680

Step 5: Simplify the Left Side
The left side simplifies to:
30×16×83840=1
So the equation becomes:
1=M2×10×127680

Step 6: Solve for M2
Now, cross-multiply to solve for M2:
M2×10×12=7680
M2×120=7680
M2=7680120
M2=64

Final Answer
Thus, the number of men needed to complete the second work is 64 men.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    Thirty men can do a piece of work in 16 days working 8 hours a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 working a day?
    The following are the steps involved in solving the above problem. Arrange them in sequential order.
    M2=30×16×8×2xx×12×10
    30×16×8x=M2×12×102x
    M1D1H1W1=M2D2H2W2
    M2=64

    ACBAD
    BACBD
    CABCD
    DBACD
  • Question 2 - Select One

    Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

    A18
    B54
    C63
    D70
  • Question 3 - Select One

    Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

    A18
    B54
    C63
    D70