Thirty men can do a piece of work in 16 days working 8 hours a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 working a day?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
M2=30×16×8×2xx×12×10
30×16×8x=M2×12×102x
M1D1H1W1=M2D2H2W2
M2=64
CBAD
ACBD
ABCD
BACD
The correct Answer is:A
To solve the problem step-by-step, we can follow the logical sequence of calculations based on the information given. Here’s how we can derive the solution:
Step 1: Understand the Given Information
We know that:
- 30 men can complete a piece of work in 16 days working 8 hours a day.
- We need to find out how many men (M2) are needed to complete another work, which is twice the first one (W2 = 2 * W1), in 10 days working 12 hours a day.
Step 2: Calculate the Total Work Done in the First Scenario
The total work (W1) can be calculated as:
W1=Number of men×Number of days×Number of hours per day
W1=30 men×16 days×8 hours/day
W1=3840 man-hours
Step 3: Calculate the Total Work for the Second Scenario
Since the second work is twice the first work:
W2=2×W1=2×3840=7680 man-hours
Step 4: Set Up the Equation Using the Work Formula
Using the formula for work:
M1×D1×H1W1=M2×D2×H2W2
Substituting the known values:
30×16×83840=M2×10×127680
Step 5: Simplify the Left Side
The left side simplifies to:
30×16×83840=1
So the equation becomes:
1=M2×10×127680
Step 6: Solve for M2
Now, cross-multiply to solve for M2:
M2×10×12=7680
M2×120=7680
M2=7680120
M2=64
Final Answer
Thus, the number of men needed to complete the second work is 64 men.
---
We know that:
- 30 men can complete a piece of work in 16 days working 8 hours a day.
- We need to find out how many men (M2) are needed to complete another work, which is twice the first one (W2 = 2 * W1), in 10 days working 12 hours a day.
The total work (W1) can be calculated as:
W1=Number of men×Number of days×Number of hours per day
W1=30 men×16 days×8 hours/day
W1=3840 man-hours
Since the second work is twice the first work:
W2=2×W1=2×3840=7680 man-hours
Using the formula for work:
M1×D1×H1W1=M2×D2×H2W2
Substituting the known values:
30×16×83840=M2×10×127680
The left side simplifies to:
30×16×83840=1
So the equation becomes:
1=M2×10×127680
Now, cross-multiply to solve for M2:
M2×10×12=7680
M2×120=7680
M2=7680120
M2=64
Thus, the number of men needed to complete the second work is 64 men.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Essay Type Question5videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
View SolutionA piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?
View Solution
Knowledge Check
- Question 1 - Select One
Thirty men can do a piece of work in 16 days working 8 hours a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 working a day?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
M2=30×16×8×2xx×12×10
30×16×8x=M2×12×102x
M1D1H1W1=M2D2H2W2
M2=64ACBADBACBDCABCDDBACD - Question 2 - Select One
Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
A18B54C63D70 - Question 3 - Select One
Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
A18B54C63D70
A piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?
View Solution12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work? 28 b. 36 c. 48 d. 52
View SolutionTwelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
View SolutionTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution