A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?
11
9
8
6
The correct Answer is:D
Let A work for x days , B for (x-1) days and C for (x-5) days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
View Solution
Knowledge Check
- Question 1 - Select One
A can do a piece of work in 18 days, B in36 days and C in 54 days. A starts the work and is joined by B after 1 day, C joins them after 4 more days. How many more days will be required to complete the work?
A11B9C8D6 - Question 2 - Select One
A alone can do a certain job in 15 days , while B alone can do it in 10 days . A started the work and was joined by B after 5 days. The work lasted for how many days?
A4B8C5D9 - Question 3 - Select One
A can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
A10B12C15D16
A can do a work in 10 days and that of B in 15 days . B starts the work alone but after 3 days he left the work & A joined the work . In how many days will the total work be finished ?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View SolutionA can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a work in 18 days, B in 9 days and C in 6 days. A and B start working together and after 2 days C joins them. What is the total number of days taken to finish the work ?
View SolutionA can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is
View Solution