A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?
The correct Answer is:4 days
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so A's work per day = 1/12 of the work.
- B can complete the work in 18 days, so B's work per day = 1/18 of the work.
Step 2: Find the total work in terms of units.
- To find a common unit of work, we can take the LCM of 12 and 18.
- LCM(12, 18) = 36 units of work.
Step 3: Calculate the efficiency of A and B in terms of units.
- A's efficiency = 36 units / 12 days = 3 units per day.
- B's efficiency = 36 units / 18 days = 2 units per day.
Step 4: Set up the equation for the total work done.
- Let X be the number of days A and B worked together before A left.
- In X days, the work done by A and B together = (A's efficiency + B's efficiency) * X = (3 + 2) * X = 5X units.
- After A left, B completed the remaining work in 8 days. The work done by B in 8 days = B's efficiency * 8 = 2 * 8 = 16 units.
Step 5: Write the equation for total work.
- Total work = Work done by A and B together + Work done by B alone.
- Therefore, we have: 36 = 5X + 16.
Step 6: Solve for X.
- Rearranging the equation: 5X = 36 - 16.
- This simplifies to: 5X = 20.
- Dividing both sides by 5 gives: X = 4.
Conclusion:
- A left the work after 4 days.
- A can complete the work in 12 days, so A's work per day = 1/12 of the work.
- B can complete the work in 18 days, so B's work per day = 1/18 of the work.
- To find a common unit of work, we can take the LCM of 12 and 18.
- LCM(12, 18) = 36 units of work.
- A's efficiency = 36 units / 12 days = 3 units per day.
- B's efficiency = 36 units / 18 days = 2 units per day.
- Let X be the number of days A and B worked together before A left.
- In X days, the work done by A and B together = (A's efficiency + B's efficiency) * X = (3 + 2) * X = 5X units.
- After A left, B completed the remaining work in 8 days. The work done by B in 8 days = B's efficiency * 8 = 2 * 8 = 16 units.
- Total work = Work done by A and B together + Work done by B alone.
- Therefore, we have: 36 = 5X + 16.
- Rearranging the equation: 5X = 36 - 16.
- This simplifies to: 5X = 20.
- Dividing both sides by 5 gives: X = 4.
- A left the work after 4 days.
Topper's Solved these Questions
Similar Questions
A can do a piece of work in 20 days and B can do same work in 15 days. Both A and B start the work and after some days B left and A complete the remaining work in 6 days. After how many days will B left work?
View SolutionA can do a piece of work in 10 days and B can do same work in 15 days. Both A and B start the work and after 3 days B left. In how many days will A do the remaining work?
View Solution
Knowledge Check
- Question 1 - Select One
(A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
A18,15.,20B30,20,10C10,15,25D15,10,25 - Question 2 - Select One
A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
A9 daysB8 daysC10 daysD12 days
A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?
View SolutionA and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days. A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in 16 days. A work for 5 days, B works for 7 days and C completed the remaining work in 13 days. In how many days will A, B and C do this work alone ?
View Solution(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?
View SolutionA can do a piece of work in 30 days and B can do same work in 60 days. In how many days will A & B do this work together ?
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View Solution