Doubtnut Promotions Sticky

A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:4 days


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the work done by A and B in one day.
- A can complete the work in 12 days, so A's work per day = 1/12 of the work.
- B can complete the work in 18 days, so B's work per day = 1/18 of the work.

Step 2: Find the total work in terms of units.
- To find a common unit of work, we can take the LCM of 12 and 18.
- LCM(12, 18) = 36 units of work.

Step 3: Calculate the efficiency of A and B in terms of units.
- A's efficiency = 36 units / 12 days = 3 units per day.
- B's efficiency = 36 units / 18 days = 2 units per day.

Step 4: Set up the equation for the total work done.
- Let X be the number of days A and B worked together before A left.
- In X days, the work done by A and B together = (A's efficiency + B's efficiency) * X = (3 + 2) * X = 5X units.
- After A left, B completed the remaining work in 8 days. The work done by B in 8 days = B's efficiency * 8 = 2 * 8 = 16 units.

Step 5: Write the equation for total work.
- Total work = Work done by A and B together + Work done by B alone.
- Therefore, we have: 36 = 5X + 16.

Step 6: Solve for X.
- Rearranging the equation: 5X = 36 - 16.
- This simplifies to: 5X = 20.
- Dividing both sides by 5 gives: X = 4.

Conclusion:
- A left the work after 4 days.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    (A + B) can do a piece of work in 12 days. (B + C) can do same work in 623 days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

    A18,15.,20
    B30,20,10
    C10,15,25
    D15,10,25
  • Question 2 - Select One

    A can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?

    A9 days
    B8 days
    C10 days
    D12 days