The number of workers and time taken to complete the work varies ______ with each other.
directly
inversely
sometimes directly sometimes inversely
none of these
The correct Answer is:B
Similar Questions
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
01:36View SolutionThe following table shows the frequency distribution of the time required for each worker to complete a work. From the table find the mean time required to complete the job for a worker.
04:56View Solutionनिम्नलिखित में कौन राशि एक दूसरे के अनुक्रम या व्युत्क्रम विचरण करते हैं ?
किसी काम को पूरा करने के लिए मजदूरों की संख्या (x) तथा दिनों की संख्या (y)03:21View SolutionWhich of the following statements are of inverse variation?
Number of workers on a job and time taken by them to complete the job.01:47View Solutionकाम करने वाले व्यक्तियों की संख्या और किसी काम को पूरा करने में लगा समय।
02:17View Solution45 मजदूर एक काम को 27 दिनों में पूरा करते हैं तो कितने मजदूर उसी काम को 15 दिनों में पूरा करेंगे?
View SolutionA work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
03:24View SolutionA company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was
04:37View Solution