Doubtnut Promotions Sticky

A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was

A

100

B

300

C

600

D

200

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:A

|
Answer

Step by step video, text & image solution for A company employed 200 workers to complete a certain work in 150 days. If only one-fourth of the work has been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.

    A6 days
    B5 days
    C4 days
    D3 days
  • Question 2 - Select One

    If B can do three-fourth of a work in 3 days, then the time taken to complete the whole work is ____.

    A6 days
    B5 days
    C4 days
    D3 days
  • Question 3 - Select One

    If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

    A96 days
    B128 days
    C64 days
    D118 days