Doubtnut Promotions Sticky

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

A

100

B

110

C

55

D

50

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we can follow these instructions:

Step 1: Define the variables
Let the original number of workers be X.

Step 2: Set up the equation for the work done
If X workers can complete the work in 100 days, then the total work can be expressed in terms of worker-days:
Total Work=X×100

Step 3: Set up the equation for the work done with fewer workers
If 10 workers are absent, then the number of workers becomes X10. These workers complete the same amount of work in 110 days:
Total Work=(X10)×110

Step 4: Set the two expressions for total work equal to each other
Since both expressions represent the same total work, we can set them equal:
X×100=(X10)×110

Step 5: Expand and simplify the equation
Expanding the right side:
100X=110X1100

Step 6: Rearrange the equation to isolate X
Now, let's move all terms involving X to one side and the constant to the other side:
100X110X=1100
10X=1100

Step 7: Solve for X
Dividing both sides by -10 gives:
X=110010=110

Conclusion
The original number of workers was 110.

---

|
Updated on:7/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:

    A100
    B110
    C55
    D50
  • Question 2 - Select One

    A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    Aa. 10%
    Bb. 1427%
    Cc. 20%
    Dd. can't be determined
  • Question 3 - Select One

    A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers?

    A10%
    B1427%
    C20%
    Dcan’t be determined