A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the reasoning provided in the video transcript and break it down into clear steps:

Step 1: Determine the total work
Let the total work be represented as W. According to the problem, after 25 days, 25 of the work is completed. Therefore, the remaining work is:
Remaining Work=W25W=35W

Step 2: Calculate the initial work done
Initially, 105 men are working for 8 hours a day. The total work done in 25 days can be calculated as:
Work Done=Number of Men×Hours per Day×Days=105×8×25
Calculating this gives:
Work Done=105×8×25=21000 man-hours

Step 3: Calculate the total work
Since 25 of the work is completed in 21000 man-hours, we can find the total work W:
25W=21000W=21000×52=52500 man-hours

Step 4: Calculate the remaining work
Now, we can find the remaining work:
Remaining Work=35W=35×52500=31500 man-hours

Step 5: Determine the time left to complete the work
Since 25 days have passed, there are 25 days left to complete the work.

Step 6: Calculate the new working hours per day
Each man is now working 9 hours a day. Therefore, the total man-hours available in the remaining 25 days with 105+x men is:
Total Man-Hours Available=(105+x)×9×25

Step 7: Set up the equation
We need the total man-hours available to equal the remaining work:
(105+x)×9×25=31500

Step 8: Simplify the equation
Dividing both sides by 225 (since 9×25=225):
105+x=31500225
Calculating the right side:
31500225=140

Step 9: Solve for x
Now, we can solve for x:
105+x=140x=140105=35

Conclusion
Thus, the number of additional men required to complete the work on time is:
35

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A35
    B40
    C45
    DNone of these
  • A contract is to be completed in 50 days and 105 men were
    set to work, each working 8 h a day. After 25 days, 2/5 th of
    the work is finished. How many additional men be employed,
    so that the work may be completed on time, each man now
    working 9 h a day?

    A34
    B36
    C35
    D37
  • A contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?

    A34
    B36
    C35
    D37