A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
To solve the problem step by step, we will follow the reasoning provided in the video transcript and break it down into clear steps:
Step 1: Determine the total work
Let the total work be represented as W. According to the problem, after 25 days, 25 of the work is completed. Therefore, the remaining work is:
Remaining Work=W−25W=35W
Step 2: Calculate the initial work done
Initially, 105 men are working for 8 hours a day. The total work done in 25 days can be calculated as:
Work Done=Number of Men×Hours per Day×Days=105×8×25
Calculating this gives:
Work Done=105×8×25=21000 man-hours
Step 3: Calculate the total work
Since 25 of the work is completed in 21000 man-hours, we can find the total work W:
25W=21000⟹W=21000×52=52500 man-hours
Step 4: Calculate the remaining work
Now, we can find the remaining work:
Remaining Work=35W=35×52500=31500 man-hours
Step 5: Determine the time left to complete the work
Since 25 days have passed, there are 25 days left to complete the work.
Step 6: Calculate the new working hours per day
Each man is now working 9 hours a day. Therefore, the total man-hours available in the remaining 25 days with 105+x men is:
Total Man-Hours Available=(105+x)×9×25
Step 7: Set up the equation
We need the total man-hours available to equal the remaining work:
(105+x)×9×25=31500
Step 8: Simplify the equation
Dividing both sides by 225 (since 9×25=225):
105+x=31500225
Calculating the right side:
31500225=140
Step 9: Solve for x
Now, we can solve for x:
105+x=140⟹x=140−105=35
Conclusion
Thus, the number of additional men required to complete the work on time is:
35
Let the total work be represented as W. According to the problem, after 25 days, 25 of the work is completed. Therefore, the remaining work is:
Remaining Work=W−25W=35W
Initially, 105 men are working for 8 hours a day. The total work done in 25 days can be calculated as:
Work Done=Number of Men×Hours per Day×Days=105×8×25
Calculating this gives:
Work Done=105×8×25=21000 man-hours
Since 25 of the work is completed in 21000 man-hours, we can find the total work W:
25W=21000⟹W=21000×52=52500 man-hours
Now, we can find the remaining work:
Remaining Work=35W=35×52500=31500 man-hours
Since 25 days have passed, there are 25 days left to complete the work.
Each man is now working 9 hours a day. Therefore, the total man-hours available in the remaining 25 days with 105+x men is:
Total Man-Hours Available=(105+x)×9×25
We need the total man-hours available to equal the remaining work:
(105+x)×9×25=31500
Dividing both sides by 225 (since 9×25=225):
105+x=31500225
Calculating the right side:
31500225=140
Now, we can solve for x:
105+x=140⟹x=140−105=35
Thus, the number of additional men required to complete the work on time is:
35
Topper's Solved these Questions
Similar Questions
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View Solution
Knowledge Check
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A35B40C45DNone of theseA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?A34B36C35D37A contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
A34B36C35D37
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
View SolutionA contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
View SolutionA contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
View Solution90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
View Solution