A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

A

495

B

514

C

528

D

532

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will break down the information given and calculate the required values.

Step 1: Understand the total work and the initial conditions
- Total days to complete the work = 75 days
- Number of men initially employed = 187 men
- Hours worked per day by each man = 15 hours

Step 2: Calculate the total work in man-hours
Total work can be calculated as:
Total Work=Number of Men×Hours per Day×Total Days
Total Work=187×15×75
Calculating this gives:
Total Work=187×15=2805 man-hours
Total Work=2805×75=210375 man-hours

Step 3: Calculate the work completed in 65 days
After 65 days, it is given that 35 of the work is completed. Therefore, the work done is:
Work Done=35×Total Work
Calculating this gives:
Work Done=35×210375=126225 man-hours

Step 4: Calculate the remaining work
The remaining work to be completed is:
Remaining Work=Total WorkWork Done
Calculating this gives:
Remaining Work=210375126225=84150 man-hours

Step 5: Calculate the time left to complete the remaining work
The time left to complete the work is:
Time Left=7565=10 days

Step 6: Calculate the total man-hours available with the new working hours
Each man now works 17 hours per day. Therefore, the total man-hours available with the current workforce (187 men) in the remaining 10 days is:
Available Man-Hours=Number of Men×Hours per Day×Days Left
Calculating this gives:
Available Man-Hours=187×17×10=31790 man-hours

Step 7: Calculate the additional man-hours required
The additional man-hours required to complete the remaining work is:
Additional Man-Hours Required=Remaining WorkAvailable Man-Hours
Calculating this gives:
Additional Man-Hours Required=8415031790=52360 man-hours

Step 8: Calculate the number of additional men needed
Let x be the number of additional men required. Each man will work 17 hours per day for 10 days, so:
x×17×10=52360
x×170=52360
x=52360170=308

Step 9: Calculate the total number of men required
The total number of men required is:
Total Men=Initial Men+Additional Men=187+308=495

Step 10: Conclusion
Thus, the number of additional men that may be employed is:
Additional Men=308

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

    A162
    B234
    C262
    D81
  • A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

    A80
    B81
    C84
    D85