A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?
495
514
528
532
The correct Answer is:C
To solve the problem step by step, we will break down the information given and calculate the required values.
Step 1: Understand the total work and the initial conditions
- Total days to complete the work = 75 days
- Number of men initially employed = 187 men
- Hours worked per day by each man = 15 hours
Step 2: Calculate the total work in man-hours
Total work can be calculated as:
Total Work=Number of Men×Hours per Day×Total Days
Total Work=187×15×75
Calculating this gives:
Total Work=187×15=2805 man-hours
Total Work=2805×75=210375 man-hours
Step 3: Calculate the work completed in 65 days
After 65 days, it is given that 35 of the work is completed. Therefore, the work done is:
Work Done=35×Total Work
Calculating this gives:
Work Done=35×210375=126225 man-hours
Step 4: Calculate the remaining work
The remaining work to be completed is:
Remaining Work=Total Work−Work Done
Calculating this gives:
Remaining Work=210375−126225=84150 man-hours
Step 5: Calculate the time left to complete the remaining work
The time left to complete the work is:
Time Left=75−65=10 days
Step 6: Calculate the total man-hours available with the new working hours
Each man now works 17 hours per day. Therefore, the total man-hours available with the current workforce (187 men) in the remaining 10 days is:
Available Man-Hours=Number of Men×Hours per Day×Days Left
Calculating this gives:
Available Man-Hours=187×17×10=31790 man-hours
Step 7: Calculate the additional man-hours required
The additional man-hours required to complete the remaining work is:
Additional Man-Hours Required=Remaining Work−Available Man-Hours
Calculating this gives:
Additional Man-Hours Required=84150−31790=52360 man-hours
Step 8: Calculate the number of additional men needed
Let x be the number of additional men required. Each man will work 17 hours per day for 10 days, so:
x×17×10=52360
x×170=52360
x=52360170=308
Step 9: Calculate the total number of men required
The total number of men required is:
Total Men=Initial Men+Additional Men=187+308=495
Step 10: Conclusion
Thus, the number of additional men that may be employed is:
Additional Men=308
- Total days to complete the work = 75 days
- Number of men initially employed = 187 men
- Hours worked per day by each man = 15 hours
Total work can be calculated as:
Total Work=Number of Men×Hours per Day×Total Days
Total Work=187×15×75
Calculating this gives:
Total Work=187×15=2805 man-hours
Total Work=2805×75=210375 man-hours
After 65 days, it is given that 35 of the work is completed. Therefore, the work done is:
Work Done=35×Total Work
Calculating this gives:
Work Done=35×210375=126225 man-hours
The remaining work to be completed is:
Remaining Work=Total Work−Work Done
Calculating this gives:
Remaining Work=210375−126225=84150 man-hours
The time left to complete the work is:
Time Left=75−65=10 days
Each man now works 17 hours per day. Therefore, the total man-hours available with the current workforce (187 men) in the remaining 10 days is:
Available Man-Hours=Number of Men×Hours per Day×Days Left
Calculating this gives:
Available Man-Hours=187×17×10=31790 man-hours
The additional man-hours required to complete the remaining work is:
Additional Man-Hours Required=Remaining Work−Available Man-Hours
Calculating this gives:
Additional Man-Hours Required=84150−31790=52360 man-hours
Let x be the number of additional men required. Each man will work 17 hours per day for 10 days, so:
x×17×10=52360
x×170=52360
x=52360170=308
The total number of men required is:
Total Men=Initial Men+Additional Men=187+308=495
Thus, the number of additional men that may be employed is:
Additional Men=308
Similar Questions
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 33 days, 47 of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? 80 b. 82 c. 81 d. 83
View Solution
Knowledge Check
A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
A60B56C70D42A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?
A162B234C262D81A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?
A80B81C84D85
A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, 25 of the work is finished. How many additional men are be employed so that the work many be completed on time, each man now working 9 hours a day?
View SolutionA contract is to be completed in 50 days and 105 men were set to work, each working 8 h a day. After 25 days, 2/5th of the work is finished. How many additional men be employed, so that the work may be completed on time, each man now working 9 h a day ?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View Solution90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?
View Solution