Doubtnut Promotions Sticky

A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

A

495

B

514

C

528

D

532

Video Solution
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Questions


Knowledge Check

  • Question 1 - Select One

    A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • Question 2 - Select One

    A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

    A162
    B234
    C262
    D81
  • Question 3 - Select One

    A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

    A80
    B81
    C84
    D85