A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:56

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A60
    B56
    C70
    D42
  • A contract to be completed in 46 days and 117 men were set work, each working 8 hours per day. After 33 day, 4/7th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day ?

    A80
    B81
    C84
    D85
  • A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

    A35
    B40
    C45
    DNone of these