A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?

A

5

B

6

C

7

D

10

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we will follow these calculations:

Step 1: Determine the combined work rate of A and B
A and B together can complete the work in 3 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A and B (E_{AB})=13 (work per day)

Hint: Remember that if they can complete the work in n days, their combined efficiency is 1n.

Step 2: Calculate the work done by A and B in 2 days
In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×EAB=2×13=23

Hint: Multiply the daily work rate by the number of days worked to find the total work done.

Step 3: Determine the remaining work
The total work is considered as 1 unit. After 2 days of work, the remaining work is:
Remaining work=123=13

Hint: Subtract the work done from the total work to find the remaining work.

Step 4: Find the work done by A alone in the next 2 days
After B leaves, A continues to work alone for 2 more days to complete the remaining work. Since the remaining work is 13, we can express A's efficiency as:
Let A's efficiency (E_A)=1x (where x is the number of days A takes to complete the work alone)
In 2 days, A does:
Work done by A in 2 days=2×EA
Setting this equal to the remaining work:
2×EA=13
Thus,
EA=16 (work per day)

Hint: To find A's efficiency, divide the remaining work by the time taken to complete it.

Step 5: Calculate B's efficiency
Now we know:
EAB=EA+EB
Substituting the known values:
13=16+EB
To find EB:
EB=1316
Finding a common denominator (6):
EB=2616=16

Hint: When subtracting fractions, ensure you have a common denominator.

Step 6: Calculate the time taken by B to complete the work alone
Since EB=16, the time taken by B to complete the work alone is:
Time taken by B=1EB=116=6 days

Hint: The time taken to complete the work alone is the reciprocal of the efficiency.

Final Answer
B alone could complete the work in 6 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

    A5 days
    B6 days
    C9 days
    D10 days
  • A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?

    A45
    B90
    C60
    D120
  • A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?

    A45
    B90
    C60
    D120