A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?
5
6
7
10
The correct Answer is:B
To solve the problem step by step, we will follow these calculations:
Step 1: Determine the combined work rate of A and B
A and B together can complete the work in 3 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A and B (E_{AB})=13 (work per day)
Hint: Remember that if they can complete the work in n days, their combined efficiency is 1n.
Step 2: Calculate the work done by A and B in 2 days
In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×EAB=2×13=23
Hint: Multiply the daily work rate by the number of days worked to find the total work done.
Step 3: Determine the remaining work
The total work is considered as 1 unit. After 2 days of work, the remaining work is:
Remaining work=1−23=13
Hint: Subtract the work done from the total work to find the remaining work.
Step 4: Find the work done by A alone in the next 2 days
After B leaves, A continues to work alone for 2 more days to complete the remaining work. Since the remaining work is 13, we can express A's efficiency as:
Let A's efficiency (E_A)=1x (where x is the number of days A takes to complete the work alone)
In 2 days, A does:
Work done by A in 2 days=2×EA
Setting this equal to the remaining work:
2×EA=13
Thus,
EA=16 (work per day)
Hint: To find A's efficiency, divide the remaining work by the time taken to complete it.
Step 5: Calculate B's efficiency
Now we know:
EAB=EA+EB
Substituting the known values:
13=16+EB
To find EB:
EB=13−16
Finding a common denominator (6):
EB=26−16=16
Hint: When subtracting fractions, ensure you have a common denominator.
Step 6: Calculate the time taken by B to complete the work alone
Since EB=16, the time taken by B to complete the work alone is:
Time taken by B=1EB=116=6 days
Hint: The time taken to complete the work alone is the reciprocal of the efficiency.
Final Answer
B alone could complete the work in 6 days.
---
A and B together can complete the work in 3 days. Therefore, their combined work rate (efficiency) is:
Efficiency of A and B (E_{AB})=13 (work per day)
In 2 days, the amount of work done by A and B together is:
Work done in 2 days=2×EAB=2×13=23
The total work is considered as 1 unit. After 2 days of work, the remaining work is:
Remaining work=1−23=13
After B leaves, A continues to work alone for 2 more days to complete the remaining work. Since the remaining work is 13, we can express A's efficiency as:
Let A's efficiency (E_A)=1x (where x is the number of days A takes to complete the work alone)
In 2 days, A does:
Work done by A in 2 days=2×EA
Setting this equal to the remaining work:
2×EA=13
Thus,
EA=16 (work per day)
Now we know:
EAB=EA+EB
Substituting the known values:
13=16+EB
To find EB:
EB=13−16
Finding a common denominator (6):
EB=26−16=16
Since EB=16, the time taken by B to complete the work alone is:
Time taken by B=1EB=116=6 days
B alone could complete the work in 6 days.
Topper's Solved these Questions
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- WORK AND TIME BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION
16 Videos
- VOLUME AND SURFACE AREA BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE
111 Videos
- WORK AND WAGES BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)
7 Videos
Similar Questions
A, B and C together can complete a piece of work in 10 days. All the three started working at it together and after 4 days A left. Then B and C completed the work in 10 more days. A alone could complete the work in : a. 15 days b. 16 days c. 25 days d. 50 days
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View Solution
Knowledge Check
A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in
A5 daysB6 daysC9 daysD10 daysA and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
A45B90C60D120A and B together can complete a work in 30 days. They started together but after 6 days A left the work and the work is completed by B after 36 more days. A alone can complete the entire work in how many days?
A45B90C60D120
A and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
View SolutionA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View SolutionA can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View Solution