A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone
12,6 and 4
18,9 and 6
24,12 and 8
6,3 and 2
The correct Answer is:A
To solve the problem step by step, we will denote the time taken by B to complete the work alone as x days.
Step 1: Define the time taken by A and C
According to the problem:
- A takes twice the time taken by B, so the time taken by A is 2x days.
- A takes thrice the time taken by C, so the time taken by C can be expressed as 2x3 days.
Step 2: Calculate the work done by A, B, and C in one day
Now we can calculate the work done by each person in one day:
- Work done by A in one day = 12x
- Work done by B in one day = 1x
- Work done by C in one day = 32x
Step 3: Combine the work done by A, B, and C
When A, B, and C work together, their combined work done in one day is:
Total work in one day=12x+1x+32x
Step 4: Simplify the combined work
To combine these fractions, we need a common denominator, which is 2x:
Total work in one day=12x+22x+32x=1+2+32x=62x=3x
Step 5: Set up the equation based on the total work done in 2 days
According to the problem, working together they can complete the work in 2 days. Therefore:
Total work=1(the whole work)
So, the equation becomes:
3x×2=1
This simplifies to:
6x=1
Step 6: Solve for x
Now, we solve for x:
6=x⇒x=6
Step 7: Find the time taken by A and C
Now that we have x:
- Time taken by B = x=6 days
- Time taken by A = 2x=2×6=12 days
- Time taken by C = 2x3=2×63=4 days
Final Answer
Thus, the number of days taken by A, B, and C respectively to complete the work alone are:
- A: 12 days
- B: 6 days
- C: 4 days
According to the problem:
- A takes twice the time taken by B, so the time taken by A is 2x days.
- A takes thrice the time taken by C, so the time taken by C can be expressed as 2x3 days.
Now we can calculate the work done by each person in one day:
- Work done by A in one day = 12x
- Work done by B in one day = 1x
- Work done by C in one day = 32x
When A, B, and C work together, their combined work done in one day is:
Total work in one day=12x+1x+32x
To combine these fractions, we need a common denominator, which is 2x:
Total work in one day=12x+22x+32x=1+2+32x=62x=3x
According to the problem, working together they can complete the work in 2 days. Therefore:
Total work=1(the whole work)
So, the equation becomes:
3x×2=1
This simplifies to:
6x=1
Now, we solve for x:
6=x⇒x=6
Now that we have x:
- Time taken by B = x=6 days
- Time taken by A = 2x=2×6=12 days
- Time taken by C = 2x3=2×63=4 days
Thus, the number of days taken by A, B, and C respectively to complete the work alone are:
- A: 12 days
- B: 6 days
- C: 4 days
Topper's Solved these Questions
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - WORK AND TIME EXERCISE - EXERCISE HIGHER SKILL LEVEL QUESTION16videos
WORK AND TIME
- BOOK - ARIHANT SSCCHAPTER - VOLUME AND SURFACE AREA EXERCISE - FAST TRACK PRACTICE111videos
VOLUME AND SURFACE AREA
- BOOK - ARIHANT SSCCHAPTER - WORK AND WAGES EXERCISE - EXERCISE (HIGHER SKILL LEVEL QUESTIONS)7videos
WORK AND WAGES
Similar Questions
A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View SolutionTime taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?
View Solution
Knowledge Check
- Question 1 - Select One
A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 days - Question 2 - Select One
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days - Question 3 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30
Rahul takes twice as such time as Manick and thrice as much time a Sachin a job. If working together, they can complete the job in 4 days, find the time taken by each of them separately to complete the work.
View SolutionA takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionB is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.
View Solution