Doubtnut Promotions Sticky

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone

A

12,6 and 4

B

18,9 and 6

C

24,12 and 8

D

6,3 and 2

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we will denote the time taken by B to complete the work alone as x days.

Step 1: Define the time taken by A and C
According to the problem:
- A takes twice the time taken by B, so the time taken by A is 2x days.
- A takes thrice the time taken by C, so the time taken by C can be expressed as 2x3 days.

Step 2: Calculate the work done by A, B, and C in one day
Now we can calculate the work done by each person in one day:
- Work done by A in one day = 12x
- Work done by B in one day = 1x
- Work done by C in one day = 32x

Step 3: Combine the work done by A, B, and C
When A, B, and C work together, their combined work done in one day is:
Total work in one day=12x+1x+32x

Step 4: Simplify the combined work
To combine these fractions, we need a common denominator, which is 2x:
Total work in one day=12x+22x+32x=1+2+32x=62x=3x

Step 5: Set up the equation based on the total work done in 2 days
According to the problem, working together they can complete the work in 2 days. Therefore:
Total work=1(the whole work)
So, the equation becomes:
3x×2=1
This simplifies to:
6x=1

Step 6: Solve for x
Now, we solve for x:
6=xx=6

Step 7: Find the time taken by A and C
Now that we have x:
- Time taken by B = x=6 days
- Time taken by A = 2x=2×6=12 days
- Time taken by C = 2x3=2×63=4 days

Final Answer
Thus, the number of days taken by A, B, and C respectively to complete the work alone are:
- A: 12 days
- B: 6 days
- C: 4 days

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

    A4 days
    B6 days
    C8 days
    D12 days
  • Question 2 - Select One

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days
  • Question 3 - Select One

    A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

    A36
    B18
    C48
    D30